- AMRUT 2.0 - UWSS to Haripad Municipality
AMRUT 2.0 - UWSS to Haripad Municipality
Project |
AMRUT 2.0 - UWSS to Haripad Municipality |
Project Code |
ALPAMRUT2112213116 |
Type |
Main project |
Funding Agency |
AMRUT 2 |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
|
Description |
AMRUT 2.0 - UWSS to Haripad Municipality-- Laying transmission main to newly proposed OHSR at Thrippakudam, Providing FHTCs in Harippad Municipality, Laying distribution line, Construction of 7LL OHSR at Thrippakudam |
Status |
On-going |
District |
Alappuzha |
Executing Office |
Alappuzha Project Dn |
AS Amount (Rs) |
93850000
|
AS Number |
G.O.(Rt)No.2906/2022/LSGD |
TS Amount (Rs) |
85120000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/4832/2022_26_1_1 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
15588 |
Capacity in MLD |
7.50 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Harippad municipality area |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT 2.0 UWSS to Haripad Municipality - AMRUT 2.0 UWSS to Haripad municipality WSS to Laying Distribution Line in Haripad Municipality |
Alappuzha Project Dn |
|
2 |
Amrut 2.0 UWSS to Haripad Municipality - WSS to Haripad Municipality Construction of 7 LL OHSR at Thrippakudam in Haripad Municipality |
Alappuzha Project Dn |
|
3 |
Amrut 2.0 UWSS to Haripad Municipality - WSS to Haripad Municipality Laying Transmission main from newly proposed 7 LL OHSR at Thrippakudam in Haripad Municipality |
Alappuzha Project Dn |
|
4 |
AMRUT 2.0 UWSS to Haripad Municipality - WSS to Haripad WSS to Haripad Municipality Providing FHTCs in Haripad Municipality |
Alappuzha Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
08 May 2024 |
FHTC Work has been completed Final bill under processing and Out of total 17 Km of pipe line works, 11km of 90mm PVC laying completed. For 160mm PVC Laying for balance length of 6 Km, Work completed Final bill under processing |
Alappuzha Project Dn PM |
|
22 Apr 2024 |
FHTC Work has been completed Final bill under processing and Out of total 17 Km of pipe line works, 11km of 90mm PVC laying completed. For 160mm PVC Laying for balance length of 6 Km, Work completed Final bill under processing |
Alappuzha Project Dn PM |
|
19 Apr 2024 |
FHTC Work has been completed Final bill under processing and Out of total 17 Km of pipe line works, 11km of 90mm PVC laying completed. For 160mm PVC Laying for balance length of 6 Km, Work completed Final bill under processing |
Alappuzha Project Dn PM |
|
16 Apr 2024 |
FHTC Work has been completed Final bill under processing and Out of total 17 Km of pipe line works, 11km of 90mm PVC laying completed. For 160mm PVC Laying for balance length of 6 Km, Work completed Final bill under processing |
Alappuzha Project Dn PM |
|
10 Apr 2024 |
FHTC Work has been completed Final bill under processing and Out of total 17 Km of pipe line works, 11km of 90mm PVC laying completed. For 160mm PVC Laying for balance length of 6 Km, Work completed Final bill under processing |
Alappuzha Project Dn PM |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
18/04/2023 |
Scheduled date of Completion of the Project |
10 Jul 2023 |
Expected date of Completion |
31/12/2023 |
Processing Dates
AS Date |
24 Nov 2022 |
TS Date |
23 Jan 2023 |