AMRUT 2.0 UWSS to Haripad Municipality - AMRUT 2.0 UWSS to Haripad municipality WSS to Laying Distribution Line in Haripad Municipality

Project AMRUT 2.0 UWSS to Haripad Municipality - AMRUT 2.0 UWSS to Haripad municipality WSS to Laying Distribution Line in Haripad Municipality
Project Code ALPAMRUT112213116P1
Type Package
Main Project AMRUT 2.0 - UWSS to Haripad Municipality
Funding Agency AMRUT 2
Category AMRUT
Type of scheme Water Supply
Scheme
Description supplying and laying of 10 KM pipeline in Haripad Municipality area for providing 900 FHTC under AMRUT 2.0.
Status On-going
District Alappuzha
Executing Office Alappuzha Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 30900000
TS Number WRD/KWA-CE(CR)/EST_TS/4831/2022_26_1_1
Technical specification Supplying and Laying Distribution - 90 mm dia -11000 m & 160 mm dia - 6000m
Contractor Hasif T (Mob: 9895687298)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 21/06/2023
Scheduled date of Completion as per agreement 03 Oct 2023
Expected date of Completion Date is not specified

Processing Dates

TS Date 13 Feb 2023
Estimate Approval 13 Feb 2023
NIT Approval 03 Apr 2023
Tender Closing 07 Mar 2023
Price bid opening 08 Mar 2023

Approval Dates

Workorder Date 21 Jun 2023
NA 04 Apr 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Alappuzha Project Dn PM
Date: 20/05/2024

Work in progress | 57% Completed

Out of total 17 Km of pipe line works, 11km of 90mm PVC laying completed. For 160mm PVC Laying for balance length of 6 Km, PWD cutting sanction is awaiting. Municipality insisting that concreting to be done in Municipal roads which necessitates additional fund. .

Alappuzha Project Dn PM
Date: 19/05/2024

Work in progress | 57% Completed

Out of total 17 Km of pipe line works, 11km of 90mm PVC laying completed. For 160mm PVC Laying for balance length of 6 Km, PWD cutting sanction is awaiting. Municipality insisting that concreting to be done in Municipal roads which necessitates additional fund. .