Project | AMRUT 2.0 UWSS to Haripad Municipality - AMRUT 2.0 UWSS to Haripad municipality WSS to Laying Distribution Line in Haripad Municipality |
---|---|
Project Code | ALPAMRUT112213116P1 |
Type | Package |
Main Project | AMRUT 2.0 - UWSS to Haripad Municipality |
Funding Agency | AMRUT 2 |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | |
Description | supplying and laying of 10 KM pipeline in Haripad Municipality area for providing 900 FHTC under AMRUT 2.0. |
Status | On-going |
District | Alappuzha |
Executing Office | Alappuzha Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 30900000 |
TS Number | WRD/KWA-CE(CR)/EST_TS/4831/2022_26_1_1 |
Technical specification | Supplying and Laying Distribution - 90 mm dia -11000 m & 160 mm dia - 6000m |
Contractor | Hasif T (Mob: 9895687298) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 21/06/2023 |
---|---|
Scheduled date of Completion as per agreement | 03 Oct 2023 |
Expected date of Completion | Date is not specified |
TS Date | 13 Feb 2023 |
---|---|
Estimate Approval | 13 Feb 2023 |
NIT Approval | 03 Apr 2023 |
Tender Closing | 07 Mar 2023 |
Price bid opening | 08 Mar 2023 |
Workorder Date | 21 Jun 2023 |
---|---|
NA | 04 Apr 2023 |
Alappuzha Project Dn PM |
Date: 20/05/2024 |
Work in progress | 57% Completed
Out of total 17 Km of pipe line works, 11km of 90mm PVC laying completed. For 160mm PVC Laying for balance length of 6 Km, PWD cutting sanction is awaiting. Municipality insisting that concreting to be done in Municipal roads which necessitates additional fund. .
Alappuzha Project Dn PM |
Date: 19/05/2024 |
Work in progress | 57% Completed
Out of total 17 Km of pipe line works, 11km of 90mm PVC laying completed. For 160mm PVC Laying for balance length of 6 Km, PWD cutting sanction is awaiting. Municipality insisting that concreting to be done in Municipal roads which necessitates additional fund. .