Jal Jeevan Mission(JJM)- Alappuzha District- Providing Functional Household Tap Connections(FHTC) in Mararikulam North Grama Panchayat-(7311Nos)
| Project |
Jal Jeevan Mission(JJM)- Alappuzha District- Providing Functional Household Tap Connections(FHTC) in Mararikulam North Grama Panchayat-(7311Nos) |
| Project Code |
ALPJJM11206849 |
| Type |
Main project |
| Category |
JJM |
| Description |
Jal Jeevan Mission(JJM)- Alappuzha District- Providing Functional Household Tap Connections(FHTC) in Mararikulam North Grama Panchayat-(7311Nos) |
| District |
Alappuzha |
| Execution |
Alappuzha PH Dn |
| AS Amount (Rs) |
94400000.00 |
| Total Bill Submitted (Rs) |
8276733.00 |
| Total Bill Paid (Rs) |
-- |
| Coverage |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 03 May 2021 |
1025 Nos. FHTC Completed ( Total 7311) |
EE PHD ALP |
|
| 23 Apr 2021 |
829 FHTCs provided (Total 7311) |
EE PHD ALP |
|
| 07 Apr 2021 |
570 FHTC Completed |
EE PHD ALP |
|
| 19 Mar 2021 |
120 FHTCs Completed |
EE PHD ALP |
|
| 19 Mar 2021 |
1130. FHTCs Completed. |
EE PHD ALP |
|
No project review have been added to this project
Reported Issues
| Issue date |
Solved On |
Action Taken On |
Description |
Comments |
Issue Status |
| 23 Apr 2021 |
Pending |
Pending |
Shortage of materials |
No comments available. |
Pending |
| 07 Apr 2021 |
23 Apr 2021 |
Pending |
Contractors non cooperation |
Agreement executed on 19.4.2021 |
Solved |
| 14 Feb 2021 |
19 Apr 2021 |
Pending |
Contractors non cooperation |
Agreement Executed |
Solved |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
Al Jeevan Mission(JJM)- Alappuzha District- Providing Functional Household Tap Connections(FHTC) in Mararikulam North Grama Panchayat-(7311Nos) |
Alappuzha PH Dn |
|
Duration & Sanction dates
| Date of Sanction |
06/01/2021 |
| Date of start |
06/01/2021 |
| Expected date of Completion |
19/04/2021 |
Other details
| Project Officers |
View |
| Funding Agency |
JJM |
Processing Dates
| Administrative Sanction[AS] |
21 Aug 2020 |
| Technichal Sanction[TS] |
27 Aug 2020 |
Approval Dates
| Workorder Date |
06 Jan 2021 |