| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 03 Jul 2025 | work completed 5109 FHTC given | Alappuzha PH Dn EE | |
| 10 Apr 2023 | work completed | Alappuzha PH Sub Dn AEE | |
| 17 Mar 2023 | work completed | Alappuzha PH Sub Dn AEE | |
| 13 Dec 2022 | 4670FHTC Completed.(Total-7311)4670 FHTC Geo-tagged 4670FHTC Billed | Alappuzha PH Sub Dn AEE | |
| 08 Jul 2022 | 4423FHTC Completed.(Total-7311)4125 FHTC Geo-tagged 4423 FHTC Billed | Alappuzha PH Sub Dn AEE | |
| 06 Jul 2022 | 4423FHTC Completed.(Total-7311)4125 FHTC Geo-tagged 4423 FHTC Billed | Alappuzha PH Sub Dn AEE | |
| 24 Jun 2022 | 4125FHTC Completed.(Total-7311)4125 FHTC Geo-tagged 4057 FHTC Billed | Alappuzha PH Sub Dn AEE | |
| 04 Jun 2022 | 4125FHTC Completed.(Total-7311)4125 FHTC Geo-tagged 4057 FHTC Billed | Alappuzha PH Sub Dn AEE | |
| 28 May 2022 | 4125FHTC Completed.(Total-7311)4125 FHTC Geo-tagged 4057 FHTC Billed | Alappuzha PH Sub Dn AEE | |
| 07 May 2022 | 4140 FHTC Completed.(Total-7311) 4140 FHTC Geo-tagged . | Alappuzha PH Sub Dn AEE |