AWSS to Kollam Corporation - Improvements to water supply in Kilikollur Zone, Kadavoor and Sakthikulangara zone Providing pumping main using HDPE(For River crossing) /DI pipes of 700mm to 300mm size for a total length of 17kms from Vasoorichira towards Moonamkutty, Sakthikulangara Mathilil & Anchalumoodu, Providing pumpsets at WTP pump house - 180 HP 2nos, including road restoration charges

Project AWSS to Kollam Corporation - Improvements to water supply in Kilikollur Zone, Kadavoor and Sakthikulangara zone Providing pumping main using HDPE(For River crossing) /DI pipes of 700mm to 300mm size for a total length of 17kms from Vasoorichira towards Moonamkutty, Sakthikulangara Mathilil & Anchalumoodu, Providing pumpsets at WTP pump house - 180 HP 2nos, including road restoration charges
Project Code KLMAMRUT112214153P2
Type Package
Main Project AMRUT - 2.0 - Augmentation of Water Supply To Kollam Corporation – Distribution Improvements
Funding Agency AMRUT
Category AMRUT 2
Type of scheme Water Supply
Scheme AMRUT
Description Improvements to water supply in Kilikollur Zone, Kadavoor and Sakthikulangara zone by providing pumping main using HDPE(For River crossing) /DI pipes of 700mm to 300mm size for a total length of 17kms from Vasoorichira towards Moonamkutty, Sakthikulangara Mathilil & Anchalumoodu
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 0
TS Number
Technical specification

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
25 Jul 2022 Pending Pending Road Cut Related Risk Laying of DI pipe line of 700mm to 300mm size for a total length of 17kms from WTP,Vasoorichira to Kavnad No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 01/05/2023
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project Dn EE
Date: 19/12/2025

Work in progress | 0% Completed

Work dropped vide G.O(Rt)No. 2764/2025/LSGD dated 10.11.2025 due to non obtaining laying permission to lay Clear water transmission main through NH66. .

Kollam Project Dn EE
Date: 25/11/2025

Work has started | 0% Completed

As directed by AMRUT, KWA tendered the work with opening date on 15/02/2024.Two offers received . Price bid opened on 7/3/2024 and tender submitted for negotiation on 19/3/2024. Quoted rate is 20.22% above TPAC. In the meeting convenyed by PWD Secretary on 25/03/2024, NHAI informed that the proposed pipe line can be laid throught service road after constructing a duct. Approxiamte cost for construction of duct as per the rate provided by NHAI submitted to SMMU. The cross sectional details of duct awaiting from NHAI for preparing detailed estimate. Online application re-submitted with the proposal of construction of duct along the service road for laying DI pipe line on 22/7/2024. NHAI return back application on 3/9/2024 by stating that all relevant documents like undertakings, draft license deed are required to be attach and resubmit. Technical Approval Under Processing . .