| Project | AWSS To KOLLAM CORPORATION -Extension of distribution system for a total of 30 Kms in various zones using PVC pipes, including road restoration charges (Phase 2) |
|---|---|
| Project Code | KLMAMRUT112214153P7 |
| Type | Package |
| Main Project | AMRUT - 2.0 - Augmentation of Water Supply To Kollam Corporation – Distribution Improvements |
| Funding Agency | AMRUT |
| Category | AMRUT 2 |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | Extension of distribution system for a total of 30 Kms in various zones using PVC pipes, including road restoration charges (Phase 2) |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 0 |
| TS Number | |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 01/05/2023 |
|---|---|
| Scheduled date of Completion as per agreement | Date is not specified |
| Expected date of Completion | Date is not specified |
| Kollam Project Dn AE |
| Date: 20/12/2025 |
Work has started | 0% Completed
Work dropped vide G.O(Rt)No. 2764/2025/LSGD dated 10.11.2025 due to non obtaining laying permission from NHAI through NH66. .
| Kollam Project Dn EE |
| Date: 19/12/2025 |
Work has started | 0% Completed
Work dropped vide G.O(Rt)No. 2764/2025/LSGD dated 10.11.2025 due to non obtaining laying permission from NHAI through NH66. .