State plan- CWSS to Thrithala - Dismantling of Damaged 100 HP Starter assembley and its cabling system and supplying and fixing of new soft starter suitable for 100 HP Centrifugal moter pump set at CWSS to Thrithala

Project State plan- CWSS to Thrithala - Dismantling of Damaged 100 HP Starter assembley and its cabling system and supplying and fixing of new soft starter suitable for 100 HP Centrifugal moter pump set at CWSS to Thrithala
Project Code TCRGOK06217647
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description State plan- CWSS to Thrithala - Dismantling of Damaged 100 HP Starter assembley and its cabling system and supplying and fixing of new soft starter suitable for 100 HP Centrifugal moter pump set at CWSS to Thrithala
Status Short Closed
District Thrissur
Executing Office Thrithala Sn
AS Amount (Rs) 380000
AS Number KWA/JB/PIU-1/AE-4 State plan/OPT/05/2021-22 (II)
TS Amount (Rs) 379551
TS Number TS/2021-2022/2020/27216
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 14500
Capacity in MLD 5.50
Actual Project Completion Date Date is not specified
Coverage CWSS

Packages

No. Project Name Location View
1 State plan- CWSS to Thrithala - Dismantling of Damaged 100 HP Starter assembley and its cabling system and supplying and fixing of new soft starter suitable for 100 HP Centrifugal moter pump set at CWSS to Thrithala Thrithala Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Sep 2022 Work not started. Material has been purchased by contractor. Direction contractor for erection immediately. contractor has agreed to commence the work within a week. Thrithala PH Sn - AE
19 Sep 2022 Work not started. Material has been purchased by contractor. Direction contractor for erection immediately. contractor has agreed to commence the work within a week. Thrithala PH Sn - AE
13 Sep 2022 Work not started. Material has been purchased by contractor. Direction contractor for erection immediately.contractor has agreed to commence the work within a week. Thrithala PH Sn - AE
06 Sep 2022 Work not started. Material has been purchased by contractor. Direction contractor for erection immediately.contractor has agreed to commence the work within a week. Thrithala PH Sn - AE
30 Aug 2022 Work not started. Material has been purchased by contractor. Direction contractor for erection immediately.contractor has agreed to commence the work within a week. Thrithala PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 16/12/2021
Scheduled date of Completion of the Project 31 Mar 2022
Expected date of Completion 31/12/2022

Processing Dates

AS Date 16 Jun 2021
TS Date 16 Oct 2021

Other details

Project Officers View