State plan- CWSS to Thrithala - Dismantling of Damaged 100 HP Starter assembley and its cabling system and supplying and fixing of new soft starter suitable for 100 HP Centrifugal moter pump set at CWSS to Thrithala
State plan- CWSS to Thrithala - Dismantling of Damaged 100 HP Starter assembley and its cabling system and supplying and fixing of new soft starter suitable for 100 HP Centrifugal moter pump set at CWSS to Thrithala
Project Code
TCRGOK06217647
Type
Main project
Funding Agency
GOK
Category
State plan
Type of scheme
Water Supply
Scheme
2215-02-106-97
Description
State plan- CWSS to Thrithala - Dismantling of Damaged 100 HP Starter assembley and its cabling system and supplying and fixing of new soft starter suitable for 100 HP Centrifugal moter pump set at CWSS to Thrithala
Status
Short Closed
District
Thrissur
Executing Office
Thrithala Sn
AS Amount (Rs)
380000
AS Number
KWA/JB/PIU-1/AE-4 State plan/OPT/05/2021-22 (II)
TS Amount (Rs)
379551
TS Number
TS/2021-2022/2020/27216
Total Bill Submitted (Rs)
0
Total Bill Paid (Rs)
0
Population Benefitted
14500
Capacity in MLD
5.50
Actual Project Completion Date
Date is not specified
Coverage
CWSS
Packages
No.
Project Name
Location
View
1
State plan- CWSS to Thrithala - Dismantling of Damaged 100 HP Starter assembley and its cabling system and supplying and fixing of new soft starter suitable for 100 HP Centrifugal moter pump set at CWSS to Thrithala
Thrithala Sn
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
27 Sep 2022
Work not started. Material has been purchased by contractor. Direction contractor for erection immediately. contractor has agreed to commence the work within a week.
Thrithala PH Sn - AE
19 Sep 2022
Work not started. Material has been purchased by contractor. Direction contractor for erection immediately. contractor has agreed to commence the work within a week.
Thrithala PH Sn - AE
13 Sep 2022
Work not started. Material has been purchased by contractor. Direction contractor for erection immediately.contractor has agreed to commence the work within a week.
Thrithala PH Sn - AE
06 Sep 2022
Work not started. Material has been purchased by contractor. Direction contractor for erection immediately.contractor has agreed to commence the work within a week.
Thrithala PH Sn - AE
30 Aug 2022
Work not started. Material has been purchased by contractor. Direction contractor for erection immediately.contractor has agreed to commence the work within a week.