Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Sep 2022 | Work not started. Material has been purchased by contractor. Direction contractor for erection immediately. contractor has agreed to commence the work within a week. | Thrithala PH Sn - AE | |
19 Sep 2022 | Work not started. Material has been purchased by contractor. Direction contractor for erection immediately. contractor has agreed to commence the work within a week. | Thrithala PH Sn - AE | |
13 Sep 2022 | Work not started. Material has been purchased by contractor. Direction contractor for erection immediately.contractor has agreed to commence the work within a week. | Thrithala PH Sn - AE | |
06 Sep 2022 | Work not started. Material has been purchased by contractor. Direction contractor for erection immediately.contractor has agreed to commence the work within a week. | Thrithala PH Sn - AE | |
30 Aug 2022 | Work not started. Material has been purchased by contractor. Direction contractor for erection immediately.contractor has agreed to commence the work within a week. | Thrithala PH Sn - AE | |
27 Aug 2022 | Work not started. Material has been purchased by contractor. Direction contractor for erection immediately.contractor has agreed to commence the work within a week. | Thrithala PH Sn - AE | |
23 Aug 2022 | Work not started. Material has been purchased by contractor. Direction contractor for erection immediately.contractor has agreed to commence the work within a week. | Thrithala PH Sn - AE | |
22 Aug 2022 | to be started | Thrithala PH Sn - AE | |
16 Aug 2022 | to be started | Thrithala PH Sn - AE | |
04 Aug 2022 | to be started | Thrissur PH Dn EE |