Jal Jeevan Mission - Providing FHTC's to Wandoor Grama Panchayath in Malappuram District

Project Jal Jeevan Mission - Providing FHTC's to Wandoor Grama Panchayath in Malappuram District
Project Code MLPJJM08203770P1
Type Package
Main Project Jal Jeevan Mission - Providing FHTC's to Wandoor Grama Panchayath in Malappuram District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Providing FHTC's to Wandoor Grama Panchayath in Malappuram District
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 61000000
TS Number TS/2020-2021/2020/19120
Technical specification Laying 90 mm PVC - 6800 m, Laying 63 mm PVC - 2500 m, Laying 50 mm PVC - 2500 m, Laying 80 mm GI - 3000 m, Laying 50 mm GI - 1000 m, Laying 40 mm GI - 1000 m , Providing FHTC - 4000 Nos
Contractor O Abdul Majeed (Mob: 9447184489)

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
01 Jan 2022 Pending Pending Technical Project Risk 1155 FHTC completed. Pipe lines proposed in this project work and feasible FHTC work were completed. Storage and distribution enhancement required for providing more FHTC in this panchayath. Revised proposal given in 5 th SLSSC for approval No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 13/11/2020
Scheduled date of Completion as per agreement 31 Dec 2021
Expected date of Completion 31/03/2022

Processing Dates

TS Date 28 Aug 2020
Estimate Approval 30 Jul 2020
NIT Approval 29 Aug 2020
Tender Closing 09 Sep 2020
Technichal Pre-Qualification 01 Oct 2020
Price bid opening 01 Oct 2020

Approval Dates

Workorder Date 03 Oct 2020
NA 16 Oct 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Malappuram Project Dn AE2
Date: 01/02/2022

Work in progress | 100% Completed

The schedule quantity of pipe line work in the subject work were completed . The feasible 1156 nos FHTC out of schedule quantity 4000 nos were given from the distribution system. The balance FHTCs( western side of railway line) will be given only after the completion by enhancing the distribution system and reservoir. The proposal for Construction of OHSR and distribution system is placed in the 5th SLSSC for approval.

Malappuram Project Dn AE2
Date: 31/01/2022

Work in progress | 35% Completed

The schedule quantity of pipe line work in the subject work were completed . The feasible 1156 nos FHTC out of schedule quantity 4000 nos were given from the distribution system. The balance FHTCs( western side of railway line) will be given only after the completion by enhancing the distribution system and reservoir. The proposal for Construction of OHSR and distribution system is placed in the 5th SLSSC for approval.