Jal Jeevan Mission - Providing FHTC's to Wandoor Grama Panchayath in Malappuram District
| Project |
Jal Jeevan Mission - Providing FHTC's to Wandoor Grama Panchayath in Malappuram District |
| Project Code |
MLPJJM08203770 |
| Type |
Main project |
| Category |
JJM |
| Description |
Providing FHTC's to Wandoor Grama Panchayath in Malappuram District |
| District |
Malappuram |
| Execution |
Malappuram Project Dn |
| AS Amount (Rs) |
61400000.00 |
| Total Bill Submitted (Rs) |
9151682.59 |
| Total Bill Paid (Rs) |
7121629.00 |
| Coverage |
All ward Nos Wandoor Panchayath except 23, 22, 1, and five wards in the eastern sides of Railway line |
| Work Plan |
Download |
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 21 Apr 2021 |
Further FHTC will be given after commissioning of Thiruvali scheme which is expected before 30/04/2021 |
AE2 mlpm |
|
| 14 Apr 2021 |
Total 783 FHTC given and Tri party inspection completed for 174 Nos. Awaiting the arrival of Clear water from WSS to Thiruvali, which in the verge of commissioning. |
AE2 mlpm |
|
| 09 Mar 2021 |
CC 3rd and part bill under preparation. Third party inspection conducted partially |
AE2 mlpm |
|
| 01 Mar 2021 |
CC 3rd and part bill under preparation. Third party inspection started in ward 17 and 16 |
AE2 mlpm |
|
| 26 Jan 2021 |
Total 705 Connections given. Geo tagging completed for 692 No. CC 2nd part bill prepared and submitted |
AE2 mlpm |
|
No project review have been added to this project
Reported Issues
| Issue date |
Solved On |
Action Taken On |
Description |
Comments |
Issue Status |
| 07 Mar 2021 |
Pending |
Pending |
KSEB related issues |
No comments available. |
Pending |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
Jal Jeevan Mission - Providing FHTC's to Wandoor Grama Panchayath in Malappuram District |
Project Division Malappuram |
|
Duration & Sanction dates
| Date of Sanction |
21/08/2020 |
| Date of start |
13/11/2020 |
| Expected date of Completion |
02/04/2021 |
Other details
| Project Officers |
View |
| Funding Agency |
JJM |
Processing Dates
| Administrative Sanction[AS] |
21 Aug 2020 |
| Technichal Sanction[TS] |
28 Aug 2020 |
Approval Dates
| Workorder Date |
03 Oct 2020 |
| Agreement Date |
16 Nov 2020 |