WSS to Thevalakkara and Thekkumbhagam Panchayaths-Part-II-Balance works OF THEVALAKKARA PANCHAYATH-CONSTRUCTION OF 6.5LL OHSR AND LAYING OF 350mm DI PIPE(ARP) "

Project WSS to Thevalakkara and Thekkumbhagam Panchayaths-Part-II-Balance works OF THEVALAKKARA PANCHAYATH-CONSTRUCTION OF 6.5LL OHSR AND LAYING OF 350mm DI PIPE(ARP) "
Project Code KLMGOI1211487P1
Type Package
Main Project NRDWP-CWSS-PLAN(10)-BALANCE WORK OF THEVALAKKARA PANCHAYATH-CONSTRUCTION OF 6.5LL OHSR AND LAYING OF 350mm DI PIPE(1189)
Funding Agency GOI
Category ARP Central
Type of scheme Water Supply
Scheme
Description WSS to Thevalakkara and Thekkumbhagam Panchayaths-Part-II-Balance works(ARP) "-Construction of 6.5 lakh lit Capacity OHSR at Mariyadu Mukku Transmission main 350 mm dia DI K9 to OHSR at Mariyadumukku at Thevalakkara Panchayath and Distribution system in Thevalakkara Panchayat
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 31921000
TS Number TS/2019-2020/2019/8669 Dated: 06-11-2019
Technical specification OHSR- 6.5LL, 350mm DI K9 Pipe-1220m

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 20/08/2020
Scheduled date of Completion as per agreement 12 Mar 2021
Expected date of Completion 13/08/2021

Processing Dates

TS Date 06 Nov 2019
Estimate Approval 31 Mar 2019
NIT Approval 31 Mar 2019
Tender Closing 27 May 2019
Technichal Pre-Qualification 23 May 2019
Price bid opening 27 May 2019

Approval Dates

Workorder Date 04 Feb 2020
NA 13 Mar 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project HD
Date: 07/09/2021

Work has been completed | 100% Completed

THE WORK IS COMPLETED.

Kollam Project HD
Date: 06/09/2021

Work in progress | 98% Completed

Anchor block works in progress .