Jal Jeevan Mission (JJM)-WSS to kannur adjoining panchayaths Phase III construction of service reservoirs ,laying distribution network and providing FHTCS IN Azhikode ,Chirakkal AND Valapattanam Panchayaths -Road restoration Azhikode

Project Jal Jeevan Mission (JJM)-WSS to kannur adjoining panchayaths Phase III construction of service reservoirs ,laying distribution network and providing FHTCS IN Azhikode ,Chirakkal AND Valapattanam Panchayaths -Road restoration Azhikode
Project Code KNRJJM102316978P1
Type Package
Main Project Jal Jeevan Mission (JJM)-WSS to kannur adjoining panchayaths Phase III construction of service reservoirs ,laying distribution network and providing FHTCS IN Azhikode ,Chirakkal AND Valapattanam Panchayaths -Road restoration
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Azhikode Panchayath Road restoration work after JJM Pipe laying Distribution Network.
Status On-going
District Kannur
Executing Office Koothuparamba Project Sn No1
Agreement Number
Agreement Date
TS Amount (Rs) 46800000
TS Number 23183/2023-2024
Technical specification Road Restoration

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 25/03/2024
Scheduled date of Completion as per agreement 24 Jan 2025
Expected date of Completion 24/01/2025

Processing Dates

TS Date 01 Jan 2024
Estimate Approval 01 Jan 2024
NIT Approval 02 Jan 2024
Tender Closing 12 Jan 2024
Price bid opening 29 Feb 2024

Approval Dates

Workorder Date 29 Feb 2024
NA 15 Mar 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Koothuparamba Project Sn No 1
Date: 04/07/2025

Work in progress | 50% Completed

work in progress.

Koothuparamba Project Sn No 1
Date: 01/07/2025

Work in progress | 50% Completed

work in progress.