Jal Jeevan Mission (JJM)-WSS to kannur adjoining panchayaths Phase III construction of service reservoirs ,laying distribution network and providing FHTCS IN Azhikode ,Chirakkal AND Valapattanam Panchayaths -Road restoration
| Project |
Jal Jeevan Mission (JJM)-WSS to kannur adjoining panchayaths Phase III construction of service reservoirs ,laying distribution network and providing FHTCS IN Azhikode ,Chirakkal AND Valapattanam Panchayaths -Road restoration |
| Project Code |
KNRJJM102316978 |
| Type |
Main project |
| Funding Agency |
JJM |
| Category |
JJM |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-102-92-01 |
| Description |
Azhikode Panchayath Road restoration work after JJM Pipe laying Distribution Network. |
| Status |
On-going |
| District |
Kannur |
| Executing Office |
Koothuparamba Project Sub Dn |
| AS Amount (Rs) |
65000000
|
| AS Number |
G.O.(RT)NO.897/2023/WRD |
| TS Amount (Rs) |
46800000 |
| TS Number |
23183/2023-2024 |
| Total Bill Submitted (Rs) |
9084435 |
| Total Bill Paid (Rs) |
0 |
| Population Benefitted |
26000 |
| Capacity in MLD |
13.00 |
| Actual Project Completion Date |
24 Jan 2025 |
| Coverage |
Road restoration |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
Jal Jeevan Mission (JJM)-WSS to kannur adjoining panchayaths Phase III construction of service reservoirs ,laying distribution network and providing FHTCS IN Azhikode ,Chirakkal AND Valapattanam Panchayaths -Road restoration Azhikode |
Koothuparamba Project Sn No1 |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 06 Jan 2026 |
work in progress |
Koothuparamba Project Sn No 1 |
|
| 31 Dec 2025 |
work in progress |
Koothuparamba Project Sn No 1 |
|
| 26 Dec 2025 |
work in progress |
Koothuparamba Project Sn No 1 |
|
| 22 Dec 2025 |
work in progress |
Koothuparamba Project Sn No 1 |
|
| 17 Dec 2025 |
work in progress |
Koothuparamba Project Sn No 1 |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
25/03/2024 |
| Scheduled date of Completion of the Project |
24 Jan 2025 |
| Expected date of Completion |
31/10/2025 |
Processing Dates
| AS Date |
26 Oct 2023 |
| TS Date |
01 Jan 2024 |