Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Jun 2025 | 3 Km of pipeline laid .Work stopped due to monsoon. | Keezhallur PH Sn AE | |
17 Jun 2025 | 3 Km of pipeline laid .Work stopped due to monsoon. | Keezhallur PH Sn AE | |
12 Jun 2025 | 3 Km of pipeline laid .Work stopped due to monsoon | Keezhallur PH Sn AE | |
31 May 2025 | 3 Km of pipeline laid .Work stopped due to monsoon | Keezhallur PH Sn AE | |
22 Apr 2025 | PWD demand notice waiting. | Keezhallur PH Sn AE | |
08 Apr 2025 | PWD demand notice waiting. | Keezhallur PH Sn AE | |
01 Apr 2025 | PWD demand notice waiting. | Keezhallur PH Sn AE | |
19 Mar 2025 | PWD demand notice waiting. | Keezhallur PH Sn AE | |
05 Mar 2025 | LOA issued and Agreement executed on 12-11-2024.Pipe supplied.PWD demand notice waiting. | Keezhallur PH Sn AE | |
18 Feb 2025 | LOA issued and Agreement executed on 12-11-2024.Pipe supplied.PWD demand notice waiting. | Keezhallur PH Sn AE |