| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 30 Oct 2025 | COP submitted for road cutting permission | Keezhallur PH Sn AE | |
| 23 Oct 2025 | COP Submitted for road cutting permission. | Keezhallur PH Sn AE | |
| 15 Oct 2025 | Out of 3 PWD road cutting permissions, 2 road cutting permission received and COP submitted for the remaining one permission. | Keezhallur PH Sn AE | |
| 10 Oct 2025 | 3.1 Km of pipeline laid .PWD road crossing waiting for permission | Keezhallur PH Sn AE | |
| 03 Oct 2025 | 3.1 Km of pipeline laid .PWD road crossing waiting for permission | Keezhallur PH Sn AE | |
| 27 Sep 2025 | 3.1 Km of pipeline laid .PWD road crossing waiting for permission | Keezhallur PH Sn AE | |
| 24 Sep 2025 | 3.1 Km of pipeline laid .PWD road crossing waiting for permission | Keezhallur PH Sn AE | |
| 20 Sep 2025 | 3.1 Km of pipeline laid .PWD road crossing waiting for permission | Keezhallur PH Sn AE | |
| 25 Aug 2025 | 3.1 Km of pipeline laid .PWD road crossing waiting for permission | Keezhallur PH Sn AE | |
| 16 Aug 2025 | 3.1 Km of pipeline laid . | Keezhallur PH Sn AE |