| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 15 May 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
| 12 May 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
| 09 May 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
| 06 May 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
| 03 May 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
| 30 Apr 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
| 27 Apr 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
| 24 Apr 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
| 21 Apr 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
| 18 Apr 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 |