Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
21 Apr 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
18 Apr 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
15 Apr 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
12 Apr 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
09 Apr 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
06 Apr 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
03 Apr 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
31 Mar 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
28 Mar 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
24 Mar 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 |