Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
21 Mar 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
18 Mar 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
15 Mar 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
12 Mar 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
09 Mar 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
06 Mar 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
03 Mar 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
27 Feb 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
24 Feb 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 | |
21 Feb 2025 | Time extension request submitted up to 31.05.2025 as the second part could only be carried out after the completion of the bridge through which the pipe has to be laid | Kannur WS Sn AE 2 |