| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 Mar 2022 | 200 mm DI PIPE Laying 95%Work completed, 1764Nos FHTCs provided. | Chalakudy AE 2 | |
| 04 Mar 2022 | 200 mm DI PIPE Laying 95%Work completed, 1764Nos FHTCs provided. | Chalakudy AE 2 | |
| 03 Mar 2022 | 789 FHTCs provided (42%). DI pipe laying in progress. Pipe laying work 33% complete | Chalakudy AE 2 | |
| 02 Mar 2022 | 789 FHTCs provided (42%). DI pipe laying in progress. Pipe laying work 33% complete | Chalakudy AE 2 | |
| 28 Feb 2022 | 200 mm DI PIPE Laying 95%Work completed, 1725Nos FHTCs provided. | Chalakudy AE 2 | |
| 26 Feb 2022 | 200 mm DI PIPE Laying 95%Work completed, 1725Nos FHTCs provided. | Chalakudy AE 2 | |
| 25 Feb 2022 | 200 mm DI PIPE Laying 95%Work completed, 1725Nos FHTCs provided. | Chalakudy AE 2 | |
| 24 Feb 2022 | 200 mm DI PIPE Laying 95%Work completed, 1725Nos FHTCs provided. | Chalakudy AE 2 | |
| 23 Feb 2022 | 200 mm DI PIPE Laying 95%Work completed, 1725Nos FHTCs provided. | Chalakudy AE 2 | |
| 22 Feb 2022 | 200 mm DI PIPE Laying 95%Work completed, 1725Nos FHTCs provided. | Chalakudy AE 2 |