| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 20 Jul 2024 | 5.2 KM pipe laid 600 nos FHTC given | Kannur PH Sn 3 AE | |
| 17 Jul 2024 | 5.2 KM pipe laid 550 nos FHTC given | Kannur PH Sn 3 AE | |
| 03 Jul 2024 | 4.3 KM pipe laid 410 nos FHTC given | Kannur PH Sn 3 AE | |
| 01 Jun 2024 | 4.3 KM pipe laid 400 nos FHTC given | Kannur PH Sn 3 AE | |
| 18 May 2024 | 4 KM pipe laid 350 nos FHTC given | Kannur PH Sn 3 AE | |
| 02 May 2024 | 3 KM pipe laid 250 nos FHTC given | Kannur PH Sn 3 AE |