| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 04 Oct 2025 | 9.6 KM pipe laid 915 nos FHTC given. Road restoration-6 km | Kannur PH Sn 3 AE | |
| 10 Sep 2025 | 9.6 KM pipe laid 890 nos FHTC given. | Kannur PH Sn 3 AE | |
| 30 Aug 2025 | 9.6km pipe laid, 890 FHTC given | Kannur PH Sn 3 AE | |
| 08 Aug 2025 | 9.6 KM pipe laid 890 nos FHTC given. Road restoration-3.4km | Kannur PH Sn 3 AE | |
| 31 Jul 2025 | 9.6 KM pipe laid 890 nos FHTC given. Road restoration-3.4km | Kannur PH Sn 3 AE | |
| 19 Jul 2025 | 9.6 KM pipe laid 890 nos FHTC given. Road restoration-3.4km | Kannur PH Sn 3 AE | |
| 14 Jul 2025 | 9.6 KM pipe laid 890 nos FHTC given. Road restoration-3.4km | Kannur PH Sn 3 AE | |
| 30 Jun 2025 | 9.6 KM pipe laid 890 nos FHTC given. Road restoration-3.4km | Kannur PH Sn 3 AE | |
| 27 Jun 2025 | 9.6 KM pipe laid 890 nos FHTC given. Road restoration-3.4km | Kannur PH Sn 3 AE | |
| 23 Jun 2025 | 9.6 KM pipe laid 890 nos FHTC given. Road restoration-3.4km | Kannur PH Sn 3 AE |