| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 31 Jan 2022 | 1131/3881 FHTCS COMPLETED | Thaliparamba WS Dn EE | |
| 25 Jan 2022 | 1019/3881 FHTCS COMPLETED | Thaliparamba WS Dn EE | |
| 21 Jan 2022 | 1018/3881 FHTCS COMPLETED | Thaliparamba WS Dn EE | |
| 18 Jan 2022 | 1016/3881 FHTCS COMPLETED | Thaliparamba WS Dn EE | |
| 11 Jan 2022 | 1014/3881 FHTCS COMPLETED | Thaliparamba WS Dn EE | |
| 07 Jan 2022 | 1012/3881 FHTCS COMPLETED | Thaliparamba WS Dn EE | |
| 01 Jan 2022 | 1002/3881 FHTCS COMPLETED | Thaliparamba WS Dn EE | |
| 28 Dec 2021 | 980/3881 FHTCS COMPLETED | Thaliparamba WS Dn EE | |
| 24 Dec 2021 | 978/3881 FHTCS COMPLETED | Thaliparamba WS Dn EE | |
| 14 Dec 2021 | 963/3881 FHTCS COMPLETED | Thaliparamba WS Dn EE |