| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 14 Nov 2022 | 2661 FHTCs completed | Payyannur WS Sn - AE | |
| 10 Nov 2022 | 2661 FHTCs completed | Payyannur WS Sn - AE | |
| 08 Nov 2022 | 2642 FHTCs completed | Payyannur WS Sn - AE | |
| 04 Nov 2022 | 2642 FHTCs completed | Thaliparamba WS Dn EE | |
| 01 Nov 2022 | 2642 FHTCs completed | Thaliparamba WS Dn EE | |
| 25 Oct 2022 | 2642 FHTCs completed | Payyannur WS Sn - AE | |
| 20 Oct 2022 | 2557 FHTSc completed | Thaliparamba WS Dn EE | |
| 14 Oct 2022 | 2557 FHTSc completed | Payyannur WS Sn - AE | |
| 06 Oct 2022 | 2067 connection given | Thaliparamba WS Dn EE | |
| 03 Oct 2022 | 2067 connection given | Thaliparamba WS Dn EE |