Status Date Overall Project Status Project Officer Contact
20 Jan 2023 All structural works completed at Intake well cum pump house, Booster station and 12 MLD WTP. Electromechanical works pending , Finishing works,Compound wall works are ongoing .Balance 3080m Raw water pumping main of 400mmDI K9 & 4545m CWGM of 250mmDI to be supplied& layed by the contractor. Raw water Pump factory inspection completed on 24.12.22 but not delivered at site. CWPS to be supplied. Transformer supplied at site. Laying works of RWPM completed 2.54km from Mele Thavalam to near to Plamaram, Approach road work completed. Part bills of amount 1.41Cr pending for the payment ,CC Bill worth 1.71Cr under scrutiny in Division Office. Palakkad Proj AE 3
19 Jan 2023 All structural works completed at Intake well cum pump house, Booster station and 12 MLD WTP. Electromechanical works pending , Finishing works,Compound wall works are ongoing .Balance 3080m Raw water pumping main of 400mmDI K9 & 4545m CWGM of 250mmDI to be supplied& layed by the contractor. Raw water Pump factory inspection completed on 24.12.22 but not delivered at site. CWPS to be supplied. Transformer supplied at site. Laying works of RWPM completed 2.54km from Mele Thavalam to near to Plamaram, Approach road work completed. Part bills of amount 1.41Cr pending for the payment ,CC Bill worth 1.71Cr under scrutiny in Division Office. Palakkad Project Dn AE 4
18 Jan 2023 All structural works completed at Intake well cum pump house, Booster station and 12 MLD WTP. Electromechanical & Finishing works are ongoing .Balance 50% Raw water pumping main of 400DI& 100% CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump factory inspection completed but not delivered at site. CWPS to be supplied. Transformer supplied at site. Laying works of RWPM completed 2.54km from Mele Thavalam to near to Plamaram, Approach road work progressing. Part bills of amount 1.41Cr pending for the payment Palakkad Proj AE 3
17 Jan 2023 All structural works completed at Intake well cum pump house, Booster station and 12 MLD WTP. Electromechanical & Finishing works are ongoing .Balance 50% Raw water pumping main of 400DI& 100% CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump factory inspection completed but not delivered at site. CWPS to be supplied. Transformer supplied at site. Laying works of RWPM completed 2.00km from Mele Thavalam to near to Plamaram, Approach road work progressing. Part bills of amount 1.41Cr pending for the payment Palakkad Project Dn EE
17 Jan 2023 All structural works completed at Intake well cum pump house, Booster station and 12 MLD WTP. Electromechanical & Finishing works are ongoing .Balance 50% Raw water pumping main of 400DI& 100% CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump set factory inspection completed but not delivered at site. CWPS to be supplied. Transformer supplied at site. Laying works of RWPM completed 2.54 km from Mele Thavalam to near to Plamaram out of 3239m supplied , Approach road work completed. Two Part bills of amount 3.40Cr pending for the payment Palakkad Proj AE 3
16 Jan 2023 All structural works completed at Intake well cum pump house, Booster station and 12 MLD WTP. Electromechanical & Finishing works are ongoing .Balance 50% Raw water pumping main of 400DI& 100% CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump factory inspection completed but not delivered at site. CWPS to be supplied. Transformer supplied at site. Laying works of RWPM completed 2.00km from Mele Thavalam to near to Plamaram, Approach road work progressing. Two Part bills of amount 3.40Cr pending for the payment Palakkad Proj AE 3
13 Jan 2023 All structural works completed at Intake well cum pump house, Booster station and 12 MLD WTP. Electromechanical & Finishing works are ongoing .Balance 50% Raw water pumping main of 400DI& 100% CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump factory inspection completed but not delivered at site. CWPS to be supplied. Transformer supplied at site. Laying works of RWPM completed 2.00km from Mele Thavalam to near to Plamaram, Approach road work progressing. Two Part bills of amount 3.40Cr pending for the payment Palakkad Proj AE 3
12 Jan 2023 All structural works completed at Intake well cum pump house, Booster station and 12 MLD WTP. Electromechanical & Finishing works are ongoing .Balance 50% Raw water pumping main of 400DI& 100% CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump factory inspection completed but not delivered at site. CWPS to be supplied. Transformer supplied at site. Laying works of RWPM completed 2.00km from Mele Thavalam to near to Plamaram, Approach road work progressing. Two Part bills of amount 3.40Cr pending for the payment Palakkad Proj AE 3
11 Jan 2023 All structural works completed at Intake well cum pump house, Booster station and 12 MLD WTP. Electromechanical & Finishing works are ongoing .Balance 50% Raw water pumping main of 400DI& 100% CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump factory inspection completed but not delivered at site. CWPS to be supplied. Transformer supplied at site. Laying works of RWPM completed 2.00km from Mele Thavalam to near to Plamaram, Approach road work progressing. Two Part bills of amount 3.40Cr pending for the payment Palakkad Proj AE 3
10 Jan 2023 All structural works completed at Intake well cum pump house, Booster station and 12 MLD WTP. Electromechanical & Finishing works are ongoing .Balance 50% Raw water pumping main of 400DI& 100% CWGM of 250DI to be supplied& layed by the contractor. Raw water Pump factory inspection completed but not delivered at site. CWPS to be supplied. Transformer supplied at site. Laying works of RWPM completed 2.00km from Mele Thavalam to near to Plamaram, Approach road work progressing. Two Part bills of amount 3.40Cr pending for the payment Palakkad Proj AE 3