Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
16 Sep 2023 | Work completed Bill submitted | Chavasseryparamba WS Sn AE | |
12 Sep 2023 | Work completed Bill under preparation | Chavasseryparamba WS Sn AE | |
07 Sep 2023 | Work completed Bill under preparation | Chavasseryparamba WS Sn AE | |
31 Aug 2023 | Work completed Bill under preparation | Chavasseryparamba WS Sn AE | |
25 Aug 2023 | Work completed Bill under preparation | Chavasseryparamba WS Sn AE | |
18 Aug 2023 | Pipe Laying work completed. Water connection application submitted is under processing | Chavasseryparamba WS Sn AE | |
10 Aug 2023 | Pipe Laying work completed. Water connection application submitted is under processing | Chavasseryparamba WS Sn AE | |
02 Aug 2023 | Pipe Laying work completed. Water connection application submitted is under processing | Chavasseryparamba WS Sn AE | |
26 Jul 2023 | Pipe Laying work completed. Water connection application submitted is under processing | Chavasseryparamba WS Sn AE | |
18 Jul 2023 | Pipe Laying work completed. Connection work pending due to Non submission of water connection Application. | Chavasseryparamba WS Sn AE |