| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 11 Jul 2023 | Pipe Laying work completed. Connection work pending due to Non Submission of water connection Application. | Chavasseryparamba WS Sn AE | |
| 06 Jul 2023 | Pipe Laying work completed. Connection work pending due to Non Submission of water connection Application. | Chavasseryparamba WS Sn AE | |
| 30 Jun 2023 | Pipe Laying work completed. Connection work pending due to Non Submission of water connection Application. | Chavasseryparamba WS Sn AE | |
| 25 Jun 2023 | Pipe Laying work completed. Connection work pending due to Non Submission of water connection Application. | Chavasseryparamba WS Sn AE | |
| 21 Jun 2023 | Pipe Laying work completed. Connection work pending due to Non Submission of Application. | Kannur PH Dn EE | |
| 13 Jun 2023 | Pipe Laying work completed. Connection work pending due to Non Submission of Application. | Chavasseryparamba WS Sn AE | |
| 09 Jun 2023 | Pipe Laying work completed. Connection work pending due to Non Submission of Application. | Chavasseryparamba WS Sn AE | |
| 31 May 2023 | Work Started, Pipe Supplied | Chavasseryparamba WS Sn AE |