| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 10 Feb 2022 | Work is completed | Sulthan Bathery PH Dn EE | |
| 03 Feb 2022 | Pipe laying almost completed. FAbricaiton work in progress | Sulthan Bathery PH Dn EE | |
| 27 Jan 2022 | Pipe laying in progress, 1700m completed. | Sulthan Bathery PH Dn EE | |
| 20 Jan 2022 | Pipe laying in progress, 1500m completed. | Sulthan Bathery PH Dn EE | |
| 11 Jan 2022 | Pipe laying in progress. 700m completed. | Sulthan Bathery PH Dn EE | |
| 05 Jan 2022 | Permission obtained from PWD and work started | Sulthan Bathery PH Dn EE | |
| 04 Jan 2022 | Permission obtained from PWD and work started | Sulthan Bathery PH Dn EE | |
| 01 Jan 2022 | Permission yet not Getting | Sulthan Bathery PH Dn EE | |
| 28 Dec 2021 | Permission yet not Getting | Sulthan Bathery PH Dn EE | |