State Plan 2018-2019- ARWSS to Thirunelly- Replacement of old and damaged 100 mm GI pumping main using 150 mm DI pipes from clear water sump at Karthikulam to GLSR Anappara

Project State Plan 2018-2019- ARWSS to Thirunelly- Replacement of old and damaged 100 mm GI pumping main using 150 mm DI pipes from clear water sump at Karthikulam to GLSR Anappara
Project Code WYDGOK08182517
Type Main project
Category State plan
Description Intake well – Existing Pumping System – Existing Transmission Lines – 150 mm DI k9 pipe - 5000 m Water Treatment Plants – Existing O H Tanks – Existing G L Tank- Existing Supply lines – Existing Distribution Lines – Existing Quantity of water to be Produced – NA Expected annual revenue when project is completed – NA Ratio of material and Labor – Total cost of the project - 188.00 Lakhs
District Wayanad
Execution Sulthan Bathery PH Dn
AS Amount (Rs) 18800000.00
Total Bill Submitted (Rs) --
Total Bill Paid (Rs) --
Coverage whole scheme area

Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Mar 2021 Fund request for PWD deposit submitted to Head Office in prescribed format Sulthan Bathery PH Dn EE
25 Feb 2021 work not started. Sulthan Bathery PH Dn EE
27 Jan 2021 WORK not re start due to non getting PWD permission, Sulthan Bathery PH Dn EE
13 Nov 2020 PWD officials intimated their decision to go ahead with tarring and in such a case tar cutting sanction shall not be permitted for the next five years. Fund request(Rs.22 L) submitted to head office already and reminded of the present condition Sulthan Bathery PH Dn EE
17 Aug 2020 funds to be obtained for remitting in PWD Sulthan Bathery PH Dn EE

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Description Comments Issue Status
11 Sep 2020 Pending Pending Fund related Project Risks No comments available. Pending

Packages

No. Project Name Location View
1 State Plan 2018-2019- ARWSS to Thirunelly- Replacement of old and damaged 100 mm GI pumping main using 150 mm DI pipes from clear water sump at Karthikulam to GLSR Anappara Sulthan Bathery PH Dn

Duration & Sanction dates

Date of Sanction 20/08/2018
Date of start 13/11/2018
Expected date of Completion 31/05/2021

Other details

Project Officers View
Funding Agency GOK

Processing Dates

AS Date 20 Aug 2018
TS Date 13 Nov 2018
Estimate Approval 13 Nov 2018
Tender Closing 03 Dec 2018
Price bid opening 05 Dec 2018

Approval Dates

CE Approval 19 Dec 2018
Workorder Date 26 Dec 2018
Agreement Date 10 Jan 2019