- Home
- State Plan 2018-2019- ARWSS to Thirunell...
State Plan 2018-2019- ARWSS to Thirunelly- Replacement of old and damaged 100 mm GI pumping main using 150 mm DI pipes from clear water sump at Karthikulam to GLSR Anappara
| Project |
State Plan 2018-2019- ARWSS to Thirunelly- Replacement of old and damaged 100 mm GI pumping main using 150 mm DI pipes from clear water sump at Karthikulam to GLSR Anappara |
| Project Code |
WYDGOK08182517 |
| Type |
Main project |
| Category |
State plan |
| Description |
Intake well – Existing
Pumping System – Existing
Transmission Lines – 150 mm DI k9 pipe - 5000 m
Water Treatment Plants – Existing
O H Tanks – Existing
G L Tank- Existing
Supply lines – Existing
Distribution Lines – Existing
Quantity of water to be Produced – NA
Expected annual revenue when project is completed – NA
Ratio of material and Labor –
Total cost of the project - 188.00 Lakhs
|
| District |
Wayanad |
| Execution |
Sulthan Bathery PH Dn |
| AS Amount (Rs) |
18800000.00 |
| Total Bill Submitted (Rs) |
-- |
| Total Bill Paid (Rs) |
-- |
| Coverage |
whole scheme area |
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 08 Mar 2021 |
Fund request for PWD deposit submitted to Head Office in prescribed format |
Sulthan Bathery PH Dn EE |
|
| 25 Feb 2021 |
work not started. |
Sulthan Bathery PH Dn EE |
|
| 27 Jan 2021 |
WORK not re start due to non getting PWD permission, |
Sulthan Bathery PH Dn EE |
|
| 13 Nov 2020 |
PWD officials intimated their decision to go ahead with tarring and in such a case tar cutting sanction shall not be permitted for the next five years. Fund request(Rs.22 L) submitted to head office already and reminded of the present condition |
Sulthan Bathery PH Dn EE |
|
| 17 Aug 2020 |
funds to be obtained for remitting in PWD |
Sulthan Bathery PH Dn EE |
|
No project review have been added to this project
Reported Issues
| Issue date |
Solved On |
Action Taken On |
Description |
Comments |
Issue Status |
| 11 Sep 2020 |
Pending |
Pending |
Fund related Project Risks |
No comments available. |
Pending |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
State Plan 2018-2019- ARWSS to Thirunelly- Replacement of old and damaged 100 mm GI pumping main using 150 mm DI pipes from clear water sump at Karthikulam to GLSR Anappara |
Sulthan Bathery PH Dn |
|
Duration & Sanction dates
| Date of Sanction |
20/08/2018 |
| Date of start |
13/11/2018 |
| Expected date of Completion |
31/05/2021 |
Other details
| Project Officers |
View |
| Funding Agency |
GOK |
Processing Dates
| AS Date |
20 Aug 2018 |
| TS Date |
13 Nov 2018 |
| Estimate Approval |
13 Nov 2018 |
| Tender Closing |
03 Dec 2018 |
| Price bid opening |
05 Dec 2018 |
Approval Dates
| CE Approval |
19 Dec 2018 |
| Workorder Date |
26 Dec 2018 |
| Agreement Date |
10 Jan 2019 |