| 15 Jun 2023 | Revised AS was issued for an amount of RS 222.97 Cr. soil investigation is completed at WTP site. Contour site plan and soil report send to wascon for detailed design. DER prepared as per KIIFB template for obtaining DAR and submitted to KIIFB and uploaded in PFMS. land acquisition procedures completed. Submitted in Tar Replay | Nattika Project Dn AE 4 | |
| 14 Jun 2023 | Revised AS was issued for an amount of RS 222.97 Cr. soil investigation is completed at WTP site. Contour site plan and soil report send to wascon for detailed design. DER prepared as per KIIFB template for obtaining DAR and submitted to KIIFB and uploaded in PFMS. land acquisition procedures completed. Submitted in Tar Replay | Nattika Project Dn AE 4 | |
| 13 Jun 2023 | Revised AS was issued for an amount of RS 222.97 Cr. soil investigation is completed at WTP site. Contour site plan and soil report send to wascon for detailed design. DER prepared as per KIIFB template for obtaining DAR and submitted to KIIFB and uploaded in PFMS. land acquisition procedures completed. Submitted in Tar Replay | Nattika Project Dn AE 4 | |
| 12 Jun 2023 | Revised AS was issued for an amount of RS 222.97 Cr. soil investigation is completed at WTP site. Contour site plan and soil report send to wascon for detailed design. DER prepared as per KIIFB template for obtaining DAR and submitted to KIIFB and uploaded in PFMS. land acquisition procedures completed. Submitted in Tar Replay | Nattika Project Dn AE 4 | |
| 11 Jun 2023 | Revised AS was issued for an amount of RS 222.97 Cr. soil investigation is completed at WTP site. Contour site plan and soil report send to wascon for detailed design. DER prepared as per KIIFB template for obtaining DAR and submitted to KIIFB and uploaded in PFMS. land acquisition procedures completed. Submitted in Tar Replay | Nattika Project Dn AE 4 | |
| 10 Jun 2023 | Revised AS was issued for an amount of RS 222.97 Cr. soil investigation is completed at WTP site. Contour site plan and soil report send to wascon for detailed design. DER prepared as per KIIFB template for obtaining DAR and submitted to KIIFB and uploaded in PFMS. land acquisition procedures completed. Submitted in Tar Replay | Nattika Project Dn AE 4 | |
| 09 Jun 2023 | Revised AS was issued for an amount of RS 222.97 Cr. soil investigation is completed at WTP site. Contour site plan and soil report send to wascon for detailed design. DER prepared as per KIIFB template for obtaining DAR and submitted to KIIFB and uploaded in PFMS. land acquisition procedures completed. Submitted in Tar Replay | Nattika Project Dn AE 4 | |
| 08 Jun 2023 | Revised AS was issued for an amount of RS 222.97 Cr. soil investigation is completed at WTP site. Contour site plan and soil report send to wascon for detailed design. DER prepared as per KIIFB template for obtaining DAR and submitted to KIIFB and uploaded in PFMS. land acquisition procedures completed. Submitted in Tar Replay | Nattika Project Dn AE 4 | |
| 07 Jun 2023 | Revised AS was issued for an amount of RS 222.97 Cr. soil investigation is completed at WTP site. Contour site plan and soil report send to wascon for detailed design. DER prepared as per KIIFB template for obtaining DAR and submitted to KIIFB and uploaded in PFMS. land acquisition procedures completed. Submitted in Tar Replay | Nattika Project Dn AE 4 | |
| 06 Jun 2023 | Revised AS was issued for an amount of RS 222.97 Cr. soil investigation is completed at WTP site. Contour site plan and soil report send to wascon for detailed design. DER prepared as per KIIFB template for obtaining DAR and submitted to KIIFB and uploaded in PFMS. land acquisition procedures completed. Submitted in Tar Replay | Nattika Project Dn AE 4 |