| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 07 Mar 2024 | package 1- estimate and design procedures ongoing ,package 2&3- TS obtained ,waiting for tendering,Package 4- TS obtained waiting for tendering | Nattika Project Dn AE 4 | |
| 06 Mar 2024 | package 1- estimate and design procedures ongoing ,package 2&3- TS obtained ,waiting for tendering,Package 4- TS obtained waiting for tendering | Nattika Project Dn AE 4 | |
| 05 Mar 2024 | Package 1-Estimate sent to CE for TS approval. Package 2- TS Obtained, waiting for tendering. Package 3- TS Obtained, waiting for tendering. | Nattika Project Dn EE | |
| 03 Mar 2024 | Package 1-Estimate sent to CE for TS approval. Package 2- TS Obtained, waiting for tendering. Package 3- TS Obtained, waiting for tendering. | Nattika Project Dn EE | |
| 29 Feb 2024 | Package 1-Estimate sent to CE for TS approval. Package 2- TS Obtained, waiting for tendering. Package 3- TS Obtained, waiting for tendering. | Nattika Project Dn EE | |
| 26 Feb 2024 | Package 1-Estimate sent to CE for TS approval. Package 2- TS Obtained, waiting for tendering. Package 3- TS Obtained, waiting for tendering. | Nattika Project Dn EE | |
| 23 Feb 2024 | Package 1-Estimate sent to CE for TS approval. Package 2- TS Obtained, waiting for tendering. Package 3- TS Obtained, waiting for tendering. | Nattika Project Dn EE | |
| 20 Feb 2024 | Estimate submitted for approval. | Nattika Project Dn EE | |
| 16 Feb 2024 | Estimate submitted for approval. | Nattika Project Dn EE | |
| 12 Feb 2024 | Estimate submitted for approval. | Nattika Project Dn EE |