| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 27 Apr 2026 | Package 1 - LoA issued , soil test completed, Pipe supplied for RWPM . Package 2 & 3 - LoA issued , agreement executed, DI Pipe supply for CWGM in progress. Package 4 - TS confirmation to be obtained from KIIFB. Package 5 - completed | Nattika Project Dn AE 4 | |
| 20 Apr 2026 | Package 1 - LoA issued , soil test completed, Pipe supplied for RWPM . Package 2 & 3 - LoA issued , agreement executed, DI Pipe supply for CWGM in progress. Package 4 - TS confirmation to be obtained from KIIFB. Package 5 - completed | Nattika Project Dn AE 4 | |
| 13 Apr 2026 | Package 1 - LoA issued , soil test completed, Pipe supplied for RWPM . Package 2 & 3 - LoA issued , agreement executed, DI Pipe supply for CWGM in progress. Package 4 - TS confirmation to be obtained from KIIFB. Package 5 - completed | Nattika Project Dn AE 4 | |
| 06 Apr 2026 | Package 1 - LoA issued , soil test completed, Pipe supplied for RWPM . Package 2 & 3 - LoA issued , agreement executed, DI Pipe supply for CWGM in progress. Package 4 - TS confirmation to be obtained from KIIFB. Package 5 - completed | Nattika Project Dn AE 4 | |
| 25 Mar 2026 | Package 1 - LoA issued , soil test completed, Pipe supplied for RWPM . Package 2 & 3 - LoA issued , agreement executed, DI Pipe supply for CWGM in progress. Package 4 - TS confirmation to be obtained from KIIFB. Package 5 - completed | Nattika Project Dn EE | |
| 21 Mar 2026 | Package 1 - LoA issued , soil test completed, Pipe supplied for RWPM . Package 2 & 3 - LoA issued , agreement executed, DI Pipe supply for CWGM in progress. Package 4 - TS confirmation to be obtained from KIIFB. Package 5 - completed | Nattika Project Dn EE | |
| 18 Mar 2026 | Package 1 - LoA issued , soil test completed, Pipe supplied for RWPM . Package 2 & 3 - LoA issued , agreement executed, DI Pipe supply for CWGM in progress. Package 4 - TS confirmation to be obtained from KIIFB. Package 5 - completed | Nattika Project Dn EE | |
| 14 Mar 2026 | Package 1 - LoA issued , soil test completed, Pipe supplied for RWPM . Package 2 & 3 - LoA issued , agreement executed, DI Pipe supply for CWGM in progress. Package 4 - TS confirmation to be obtained from KIIFB. Package 5 - completed | Nattika Project Dn EE | |
| 10 Mar 2026 | Package 1 - LoA issued , soil test completed, Pipe supplied for RWPM . Package 2 & 3 - LoA issued , agreement executed, DI Pipe supply for CWGM in progress. Package 4 - TS confirmation to be obtained from KIIFB. Package 5 - completed | Nattika Project Dn EE | |
| 04 Mar 2026 | Package 1 - LoA issued , soil test completed, Pipe supplied for RWPM . Package 2 & 3 - LoA issued , agreement executed, DI Pipe supply for CWGM in progress. Package 4 - TS confirmation to be obtained from KIIFB. Package 5 - completed | Nattika Project Dn AE 4 |