Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
23 Feb 2026 Package 1 - LoA issued , soil test completed. Package 2 & 3 - LoA issued , agreement executed. Package 4 - TS confirmation to be obtained from KIIFB. Package 5 - completed Nattika Project Dn AE 4
09 Feb 2026 Package 1 - LoA issued , soil test completed. Package 2 & 3 - LoA issued , agreement executed. Package 4 - TS confirmation to be obtained from KIIFB. Package 5 - completed Nattika Project Dn AE 4
01 Mar 2026 28 Jan 2026 Package 1 - LoA issued , soil test completed, Pipe supply for RWPM completed. Package 2 & 3 - LoA issued , agreement executed , Pipe supply in progress. Package 4 - TS confirmation to be obtained from KIIFB. Package 5 - completed Nattika Project Dn AE 4
28 Jan 2026 Package 1 - LoA issued , soil test completed. Package 2 & 3 - LoA issued , agreement executed. Package 4 - TS confirmation to be obtained from KIIFB. Package 5 - completed Nattika Project Dn AE 4
23 Jan 2026 Package 1 - LoA issued , soil test completed. Package 2 & 3 - LoA issued , agreement executed. Package 4 - TS confirmation to be obtained from KIIFB. Package 5 - completed Nattika Project Dn AE 4
20 Jan 2026 TS obtained on 23/02/2024 from CE,CR,KWA & TS file uploaded in PFMS on 12.04.2024. TS confirmation obtained from KIIFB on 24-01-2025. Package approvel obtained on 05-02-2025 3 bids recieved, Finance bid opened on 16.05.2025. • Tender sanction received from CE for the L1 (M/s Koya & Company construc ltd) • DBR file submitted to KIIFB on PFMS for approval. • LOA issued to M/s Koya and company on 12/09/25 and PED Submitted in PFMS.Agreement executed on 15/10/2025.Soil sample collection completed on 18/11/2025. Design to be submitted by contractor 3 Nattika Project Dn AE 4
20 Jan 2026 Package 1 - LoA issued , soil test completed. Package 2 & 3 - LoA issued , agreement executed. Package 4 - TS confirmation to be obtained from KIIFB. Package 5 - completed Nattika Project Dn AE 4
13 Jan 2026 TS obtained on 23/02/2024 from CE,CR,KWA & TS file uploaded in PFMS on 12.04.2024. TS confirmation obtained from KIIFB on 24-01-2025. Package approvel obtained on 05-02-2025 3 bids recieved, Finance bid opened on 16.05.2025. • Tender sanction received from CE for the L1 (M/s Koya & Company construc ltd) • DBR file submitted to KIIFB on PFMS for approval. • LOA issued to M/s Koya and company on 12/09/25 and PED Submitted in PFMS.Agreement executed on 15/10/2025.Soil sample collection completed on 18/11/2025. Design to be submitted by contractor Nattika Project Dn AE 4
08 Jan 2026 Package 1 - LoA issued , soil test completed. Package 2 & 3 - LoA issued , agreement executed. Package 4 - TS confirmation to be obtained from KIIFB. Package 5 - completed Nattika Project Dn AE 4
31 Dec 2025 Package 1 - LoA issued , soil test completed. Package 2 & 3 - LoA issued , agreement executed. Package 4 - TS confirmation to be obtained from KIIFB. Package 5 - completed Nattika Project Dn AE 4