Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Jun 2025 1 LL OHSR structure work completed, plasteringcompleted . Connection work completed 926 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work pending Thaliparamba WS Sub Dn
19 Mar 2024 1 LL OHSR structure work completed, plastering progressing . Connection work in progress 526 FHTC given out of 996 FHTCs .1.6 km pipes laid out of 12 km Thaliparamba WS Dn EE
14 Mar 2024 1 LL OHSR structure work completed, plastering progressing . Connection work in progress 526 FHTC given out of 996 FHTCs .1.6 km pipes laid out of 12 km Thaliparamba WS Dn EE
13 Mar 2024 1 LL OHSR structure work completed, plastering progressing . Connection work in progress 526 FHTC given out of 996 FHTCs .1.6 km pipes laid out of 12 km Thaliparamba WS Dn EE
12 Feb 2024 1 LL OHSR structure work completed, plastering progressing . Connection work in progress 526 FHTC given out of 996 FHTCs .1.6 km pipes laid out of 12 km Thaliparamba WS Dn EE
08 Jan 2024 1 LL OHSR covering slab concrete completed , connection work in progress 450 FHTC given out of 996 FHTCs Thaliparamba WS Dn EE
09 Dec 2023 Tank work Deck slab and haunch concrete completed, side wall concrete completed, connection work in progress 150 FHTCs given Thaliparamba WS Dn EE
30 Nov 2023 tank work in progress-upto deck slab,connection work going on 100fhtc Thaliparamba WS Section
09 Nov 2023 Tank construction reached upto deck slab. Pipes supply in progress Thaliparamba WS Dn EE
07 Nov 2023 work in progress Thaliparamba WS Section