| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 28 Dec 2021 | Pack-1 Work in progress | 52% Completed | 28/12/2021 side wall first lift shuttering and reinforcement work in progress pack-2-part-1 Work in progress | 40% Completed | 28/12/2021 TOTAL 71.900 KM LAID 1.) 90 mm pvc -8 kg 20.386 km laid 2.) 90mm pvc-6 kg-36.479 KM laid 3.) 110 mm pvc 8 kg- 2.216k m laid 4.)110mm pvc -6kg-4.614Km laid 5.)140mm pvc-6kg-1.416Km 6). 160mm pvc-6kg-1.158Km laid 7).160mm pvc -8kg-0.571Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-48m, Rider main 90mm 6 kg-1.799 km laid Total 71.900km laid Pack-3 Not Started | 28/12/2021 Revised estimate prepared and submitted for approved Pack-2-part-2 Not Started | 22/12/2021 Revised estimate prepared and submitted for approval | Chittur Project Dn - AE 3 | |
| 22 Dec 2021 | Part-1 Work in progress | 37% Completed | 22/12/2021 TOTAL 70.4377KM LAID 1.) 90 mm pvc -8 kg 20.08km laid 2.) 90mm pvc-6 kg-35.532KM laid 3.) 110 mm pvc 8 kg- 2.006k m laid 4.)110mm pvc -6kg-4.614Km laid 5.)140mm pvc-6kg-1.416Km 6). 160mm pvc-6kg-1.158Km laid 7).160mm pvc -8kg-0.571Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-48m,Rider main 90mm 6 kg-1.799 km laid Total 70.4377km laid Pack-1 Work in progress | 52% Completed | 22/12/2021 side wall first lift shuttering and reinforcement work in progress pack-3 Not Started | 22/12/2021 Revised estimate prepared and submitted for approval Part-2 Not Started | 22/12/2021 Revised estimate prepared and submitted for approval | Chittur Project Dn - AE 3 | |
| 19 Dec 2021 | Pack-1 Work in progress | 51% Completed | 19/12/2021 side wall first lift shuttering and reinforcement work in progress pack-2-part-1 Work in progress | 36% Completed | 19/12/2021 TOTAL 68.073 KM LAID 1.) 90 mm pvc -8 kg 19.60 m laid 2.) 90mm pvc-6 kg-33.959KM laid 3.) 110 mm pvc 8 kg- 1.908 m laid 4.)110mm pvc -6kg-4.614Km laid 5.)140mm pvc-6kg-1.314Km 6). 160mm pvc-6kg-1.158Km laid 7).160mm pvc -8kg-0.571Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5314Km Rider main 90mm 6 kg-1.78 m laid Total 68.073km laid Pack-2-part-2 Not Started | 19/12/2021 Revised estimate prepared and submitted for approval Pack-3 Not Started | 19/12/2021 Revised estimate prepared and submitted for approval | Chittur Project Dn - AE 3 | |
| 12 Dec 2021 | Pack-1 Work in progress | 51% Completed | 12/12/2021 floor beam and slab concrete work completed and side wall reinforcement work in progress part-1 Work in progress | 36% Completed | 12/12/2021 1.) 90 mm pvc -8 kg 19.216 m laid 2.) 90mm pvc-6 kg-32.225KM laid 3.) 110 mm pvc 8 kg- 1.908 m laid 4.)110mm pvc -6kg-4.258Km laid 5.)140mm pvc-6kg-1.314Km 6). 160mm pvc-6kg-1.128Km laid 7).160mm pvc -8kg-0.571Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.089KM laid 10).250mm DI pipe-0.5314Km Rider main 90mm 6 kg-1.75 m laid Total 65.536km laid Part-2 Not Started | 12/12/2021 revised estimate prepared and submitted for approval pack-3 Not Started | 12/12/2021 work not started | Chittur Project Dn - AE 3 | |
| 05 Dec 2021 | Pack-2-part-1 Work in progress | 36% Completed | 05/12/2021 1.) 90 mm pvc -8 kg 17.344 m laid 2.) 90mm pvc-6 kg-30.931KM laid 3.) 110 mm pvc 8 kg- 1.908 m laid 4.)110mm pvc -6kg-3.862Km laid 5.)140mm pvc-6kg-1.314Km 6). 160mm pvc-6kg-1.128Km laid 7).160mm pvc -8kg-0.571Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.089KM laid 10).250mm DI pipe-0.5314Km Rider main 90mm 6 kg-1.75 m laid Total 61.974km laid Phase-2-pack-1 Work in progress | 51% Completed | 05/12/2021 floor beam and slab concrete work completed and side wall reinforcement work in progress pack-2-part-2 Not Started | 05/12/2021 revised estimate prepared and submitted for approval pack-3 Not Started | 05/12/2021 Agreement to be executed | Chittur Project Dn - AE 3 | |
| 28 Nov 2021 | Pack-1 Work in progress | 49% Completed | 28/11/2021 floor beam and slab concrete work in progress , ph-2-pack-3 Not Started | 28/11/2021 Agreement to be executed Pack-2-part-1 Work in progress | 36% Completed | 28/11/2021 1.) 90 mm pvc -8 kg 17.344 m laid 2.) 90mm pvc-6 kg-30.931KM laid 3.) 110 mm pvc 8 kg- 1.908 m laid 4.)110mm pvc -6kg-3.862Km laid 5.)140mm pvc-6kg-1.314Km 6). 160mm pvc-6kg-1.128Km laid 7).160mm pvc -8kg-0.571Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.089KM laid 10).250mm DI pipe-0.5314Km Rider main 90mm 6 kg-1.75 m laid Total 60.974km laid Pack-2-part-2 Not Started | 28/11/2021 The work has been cancelled,Revised estimate under preparation | Chittur Project Dn - AE 3 | |
| 21 Nov 2021 | Pack-1 floor beam and slab shuttering and reinforcement work in progress , pack-2-part-2 Not Started | 21/11/2021 The work has been cancelled,Revised estimate under preparation Pack-2-part-1 Work in progress | 36% Completed | 21/11/2021 1.) 90 mm pvc -8 kg 17.092m laid 2.) 90mm pvc-6 kg-29.113KM laid 3.) 110 mm pvc 8 kg-1.566 m laid 4.)110mm pvc -6kg-3.862Km laid 5.)140mm pvc-6kg-1.176Km 6). 160mm pvc-6kg-1.128Km laid 7).160mm pvc -8kg-0.571Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.056KM laid 10).250mm DI pipe-0.4424Km Rider main 90mm 6 kg-1.674 m laid Total 59.00km laid Pack-3 Not Started | 21/11/2021 Agreement to be executed , | Chittur Project Dn - AE 3 | |
| 14 Nov 2021 | pack-1 Work in progress | 47% Completed | 14/11/2021 floor beam and slab shuttering and reinforcement work in progress , pack-2-part-2 Not Started | 14/11/2021 Prequalification process to be done Pack-3 Not Started | 14/11/2021 Agreement to be executed , Pack-2-part-1 Work in progress | 36% Completed | 14/11/2021 Total 59.802km laid 1.) 90 mm pvc -8 kg 17032.50m laid 2.) 90mm pvc-6 kg-27333.00m laid 3.) 110 mm pvc 8 kg-1530.00 m laid 4.)110mm pvc -6kg-2776.00m laid 5.)140mm pvc-6kg-1176.00m 6). 160mm pvc-6kg-1128.00m laid 7).160mm pvc -8kg-571.50m laid 8).300 MM di k9-518.50m laid 9). 200mm DI K9-809.00m laid 10).250mm DI pipe-313.50m Rider main 90mm 6 kg-1277.00 m laid | Chittur Project Dn - AE 3 | |
| 07 Nov 2021 | Pack-1- Work in progress | 47% Completed | 07/11/2021 floor beam and slab shuttering and reinforcement work in progress , pack-2-part-1 Work in progress | 36% Completed | 07/11/2021 Total 59.802km laid 1.) 90 mm pvc -8 kg 17032.50m laid 2.) 90mm pvc-6 kg-27333.00m laid 3.) 110 mm pvc 8 kg-1530.00 m laid 4.)110mm pvc -6kg-2776.00m laid 5.)140mm pvc-6kg-1176.00m 6). 160mm pvc-6kg-1128.00m laid 7).160mm pvc -8kg-571.50m laid 8).300 MM di k9-518.50m laid 9). 200mm DI K9-809.00m laid 10).250mm DI pipe-313.50m Rider main 90mm 6 kg-1277.00 m laid Pack-3 Not Started | 07/11/2021 Agreement to be executed , Pack-2-part-2 -Not Started | 07/11/2021 Prequalification process to be done | Chittur Project Dn - AE 3 | |
| 31 Oct 2021 | pack-1 Work in progress | 46% Completed | 31/10/2021 floor beam and slab shuttering and reinforcement work in progress , pack-iii Not Started | 31/10/2021 Agreement to be executed , Pack-2-part-2 Not Started | 31/10/2021 Prequalification process to be done Part-1 Work in progress | 35% Completed | 31/10/2021 Total 59.802km laid 1.) 90 mm pvc -8 kg 17032.50m laid 2.) 90mm pvc-6 kg-27333.00m laid 3.) 110 mm pvc 8 kg-1530.00 m laid 4.)110mm pvc -6kg-2776.00m laid 5.)140mm pvc-6kg-1176.00m 6). 160mm pvc-6kg-1128.00m laid 7).160mm pvc -8kg-571.50m laid 8).300 MM di k9-518.50m laid 9). 200mm DI K9-809.00m laid 10).250mm DI pipe-313.50m Rider main 90mm 6 kg-1277.00 m laid | Chittur Project Dn - AE 3 |