| 22 Apr 2021 | Package III - Price bid Opened on 17/04/2021 - Submitted to CE(SR) on 19/04/2021 with LMR Comparison. Tender to be approved by Board of KWA | Kottayam PH Circle SE | |
| 21 Apr 2021 | LND AQUISTION: Meeting held with Dist Collector& SE,PHCK on 19.04.2021 to speed up the process of LA.Collector agreed to pass the order of handover of charges for LA to new office t Vaikom to facilitate contingency charges for Karimpukayam WSS *****Package III: Works are tendered.Tender commitee convened on 08.04.21 for pre-qualification and decided to pre-qualify two bidders.LMR etimate is send to HO for further processing *****Package II: Estimate Scrutiny Unit reviewed the estimate and clarifications were sought for.reply to observations were furnished on 12.04.21.Awaiting TS for the work and then it can be tendered after model code of conduct. *****Package I: Estimate send for review and approval to higher offices. | Kottayam Project Dn AE4 | |
| 17 Apr 2021 | *****Package III: Works are tendered.Tender commitee convened on 08.04.21 for pre-qualification and decided to pre-qualify two bidders. *****Package II: Estimate Scrutiny Unit reviewed the estimate and clarifications were sought for.reply to observations were furnished on 12.04.21.Awaiting TS for the work and then it can be tendered after model code of conduct. *****Package I: Estimate send for review and approval to higher offices. | Kottayam Project Dn AE4 | |
| 18 Mar 2021 | Package 1 Estimates send for approval Package 2 Estimates send for approval Package 3 Work is tendered. | Kottayam Project Dn AE4 | |
| 17 Mar 2021 | As directed by Hon MLA Sri.Jayraj Sir,formt for permissive sanction from Owners of land is send to his office for approval.On conformation,agreement for permissive sanction can be made.Details of owners are as follows: 1.Thambalakkadu site(for 8.5 LL GLSR)(8 cents)(Survey no:22/7) Sri.Varki Chethimattom 2.WTP site(for 6 MLD WTP)(50 cents) Sri.Jose Kadiyakuzhi(survey no 255/2) Sri.Elsamma Jose(survey no 255/3) Sri.Martin Kurien(survey no 254/5-1) Sri.Syric Kurien(survey no 254/3) 3.Panechapally site(for 5 LL GLSR)-Survey no 177/6(10 cents) Sri.Joe George Kallarackal Sri.Jose Abraham Kallarackal | Kottayam Project Dn AE4 | |
| 17 Mar 2021 | Status of packges are as follows" Package I Estimate is prepared and send for approval to higher offices. Package 2 Estimate is send for TS and is at CE office Package 3 Work is tendered.Tender due date was extended till 16.03.2021 | Kottayam Project Dn AE4 | |
| 23 Feb 2021 | Package I & II estimates are under scrutiny at higher offices. Package III is tendered.Tender due date is 06.03.2021 and bid opening is on 09.03.2021. Contingency charges is awited from L department.On enquiry ,it is understood that the preliminary report is send for approval | Kottayam Project Dn AE4 | |
| 16 Feb 2021 | Charges for LA acquistion handed over from Specil Tahsildar to Vaikom Tahsildar as per latest order recieved from Dist Collector.Contingency charges for LA awaited | Kottayam Project Dn AE4 | |
| 12 Feb 2021 | Awaiting for Contingency charges from LA deprtment | Kottayam Project Dn AE4 | |
| 10 Feb 2021 | Issues with LA process for proposed land at Panechapally is resolved.LA surveyor was able to plot the boundaries of proposed land for acquisition and thus at present no actions are pending from KWA side.Preliminary report on land details at Panechapally is in preparation at LA office.We are awaiting contingency charge request from Dist Collector through LA.Regarding tendering of packages,TS for package 3 is recieved.Work is tendered.Estimates for other 2 packages have been send for review and approval to higher offices. | Kottayam Project Dn AE4 |