| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 21 Oct 2024 | work started FHTC given - 52 Nos | Mattannur WS Sn | |
| 16 Oct 2024 | work started FHTC given - 45 Nos | Mattannur WS Sn | |
| 03 Oct 2024 | work started FHTC given - 23 Nos | Mattannur WS Sn | |
| 27 Sep 2024 | work started FHTC given - 18 Nos | Mattannur WS Sn | |
| 05 Sep 2024 | work not started | Mattannur WS Sn | |
| 28 Aug 2024 | work not started | Mattannur WS Sn | |
| 21 Aug 2024 | work not started | Mattannur WS Sn | |
| 06 Aug 2024 | work not started | Mattannur WS Sn | |
| 31 Jul 2024 | work not started | Mattannur WS Sn |