| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 22 Sep 2025 | FHTC given - 613 Nos, FHTC Providing work in progress, work is delaying due to intermittent rain | Mattannur WS Sn | |
| 12 Sep 2025 | FHTC given - 510 Nos, Pipe laying work in progress. (18.8km Completed). work held up due to heavy rain | Mattannur WS Sn | |
| 19 Aug 2025 | FHTC given - 510 Nos, Pipe laying work in progress. (18.8km Completed). work held up due to heavy rain | Mattannur WS Sn | |
| 31 Jul 2025 | FHTC given - 510 Nos, Pipe laying work in progress. (18.8km Completed). work held up due to heavy rain | Mattannur WS Sn | |
| 21 Jul 2025 | FHTC given - 510 Nos, Pipe laying work in progress. (18.8km Completed). work held up due to heavy rain | Mattannur WS Sn | |
| 30 Jun 2025 | FHTC given - 510 Nos, Pipe laying work in progress. (18.8km Completed). work held up due to heavy rain | Mattannur WS Sn | |
| 18 Jun 2025 | FHTC given - 510 Nos, Pipe laying work in progress. (18.8km Completed). work held up due to heavy rain | Mattannur WS Sn | |
| 14 May 2025 | FHTC given - 510 Nos, Pipe laying work in progress. (14km Completed) | Mattannur WS Sn | |
| 30 Apr 2025 | FHTC given - 510 Nos, Pipe laying work in progress. (14km Completed) | Mattannur WS Sn | |
| 16 Apr 2025 | FHTC given - 510 Nos, Pipe laying work in progress. (14km Completed) | Mattannur WS Sn |