Overall Project Status

Status Date Overall Project Status Project Officer Contact
28 Jan 2025 FHTC given - 360 Nos, Pipe laying work in progress. (10km Completed) Mattannur WS Sn
20 Jan 2025 FHTC given - 360 Nos, Pipe laying work in progress. (10km Completed) Mattannur WS Sn
12 Jan 2025 FHTC given - 240 Nos, Pipe laying work in progress. Mattannur WS Sn
06 Jan 2025 FHTC given - 215 Nos, Pipe laying work in progress. Mattannur WS Sn
01 Jan 2025 FHTC given - 199 Nos, Pipe laying work in progress. Mattannur WS Sn
26 Dec 2024 FHTC given - 187 Nos, Pipe laying work in progress. Mattannur WS Sn
18 Dec 2024 work started FHTC given - 135 Nos, Pipe laying work in progress. Mattannur WS Sn
18 Dec 2024 work started FHTC given - 100 Nos, Pipe laying work in progress Mattannur WS Sn
12 Dec 2024 work started FHTC given - 100 Nos, Pipe laying work in progress Mattannur WS Sn
03 Dec 2024 work started FHTC given - 100 Nos, Pipe laying work in progress Mattannur WS Sn