Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
29 Nov 2021 | estimate under preparation based on new rate | Edappal Sn AE | |
22 Nov 2021 | Estimate under preparation | Edappal Sn AE | |
17 Nov 2021 | estimate under preparation based on new rates | Edappal Sn AE | |
08 Nov 2021 | estimate under preparation based on new rates | Edappal Sn AE | |
01 Oct 2021 | Estimate to be finalised after approval of PVC pipe rates. | Edappal PH Dn EE |