Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
17 May 2022 | 2022 As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5 thSLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan Edappal Sn AE 30 March | Edappal Sn AE | |
13 May 2022 | 2022 As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5 thSLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan Edappal Sn AE 30 March | Edappal Sn AE | |
04 May 2022 | 2022 As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5 thSLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan Edappal Sn AE 30 Ma | Edappal Sn AE | |
28 Apr 2022 | 2022 As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5 thSLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan Edappal Sn AE 30 Mar | Edappal Sn AE | |
27 Apr 2022 | As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5 thSLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan | Edappal Sn AE | |
27 Apr 2022 | As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5 thSLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan | Edappal Sn AE | |
18 Apr 2022 | As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5 thSLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan | Edappal Sn AE | |
08 Apr 2022 | As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5 thSLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan | Edappal Sn AE | |
30 Mar 2022 | As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5 thSLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan | Edappal Sn AE | |
19 Mar 2022 | As reported by AEE Ponnani in the review meeting 12/01/2022,the revised proposal for upgrading existing gravity to 600 mm has obtained 5 thSLSSC approval under JJM and hence request submitted to SE PHC Malappuram to cancel AS of the work under Stateplan | Edappal Sn AE |