Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
23 Jul 2024 | 3 KM pipe laid 205 nos FHTC given | Kannur PH Sn 3 AE | |
03 Jul 2024 | 3 KM pipe laid 205 nos FHTC given | Kannur PH Sn 3 AE | |
01 Jun 2024 | 3 KM pipe laid 200 nos FHTC given | Kannur PH Sn 3 AE | |
18 May 2024 | 1.8 KM pipe laid 75 nos FHTC given | Kannur PH Sn 3 AE | |
02 May 2024 | 150 M pipe laid 32 nos FHTC given | Kannur PH Sn 3 AE |