| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 17 Jun 2025 | 8 KM pipe laid 680 nos FHTC given. road restoration-6.76KM | Kannur PH Sn 3 AE | |
| 29 May 2025 | 7.8 KM pipe laid 660 nos FHTC given. road restoration-7km | Kannur PH Sn 3 AE | |
| 19 May 2025 | 7.8 KM pipe laid 660 nos FHTC given. road restoration-7km | Kannur PH Sn 3 AE | |
| 03 May 2025 | 7.8 KM pipe laid 660 nos FHTC given | Kannur PH Sn 3 AE | |
| 29 Mar 2025 | 7.8 KM pipe laid 630 nos FHTC given | Kannur PH Sn 3 AE | |
| 27 Mar 2025 | 7.8 KM pipe laid 600 nos FHTC given | Kannur PH Sn 3 AE | |
| 03 Mar 2025 | 7.8 KM pipe laid 600 nos FHTC given | Kannur PH Sn 3 AE | |
| 22 Feb 2025 | 7.8 KM pipe laid 580 nos FHTC given | Kannur PH Sn 3 AE | |
| 12 Feb 2025 | 7.8 KM pipe laid 580 nos FHTC given | Kannur PH Sn 3 AE | |
| 07 Feb 2025 | 7.8 KM pipe laid 580 nos FHTC given | Kannur PH Sn 3 AE |