Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
04 Jan 2025 | 7.8 KM pipe laid 550 nos FHTC given | Kannur PH Sn 3 AE | |
17 Dec 2024 | 7.8 KM pipe laid 510 nos FHTC given | Kannur PH Sn 3 AE | |
06 Dec 2024 | 6.5 KM pipe laid 450 nos FHTC given | Kannur PH Sn 3 AE | |
22 Nov 2024 | 6.3 KM pipe laid 450 nos FHTC given | Kannur PH Sn 3 AE | |
16 Nov 2024 | 6 KM pipe laid 410 nos FHTC given | Kannur PH Sn 3 AE | |
12 Nov 2024 | 5.5 KM pipe laid 401 nos FHTC given | Kannur PH Sn 3 AE | |
07 Nov 2024 | 5 KM pipe laid 401 nos FHTC given | Kannur PH Sn 3 AE | |
04 Nov 2024 | 4 KM pipe laid 401 nos FHTC given | Kannur PH Sn 3 AE | |
02 Nov 2024 | 4 KM pipe laid 401 nos FHTC given | Kannur PH Sn 3 AE | |
01 Nov 2024 | 4 KM pipe laid 401 nos FHTC given | Kannur PH Sn 3 AE |