Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Feb 2025 7.8 KM pipe laid 580 nos FHTC given Kannur PH Sn 3 AE
29 Jan 2025 7.8 KM pipe laid 580 nos FHTC given Kannur PH Sn 3 AE
24 Jan 2025 7.8 KM pipe laid 580 nos FHTC given Kannur PH Sn 3 AE
22 Jan 2025 7.8 KM pipe laid 580 nos FHTC given Kannur PH Sn 3 AE
18 Jan 2025 7.8 KM pipe laid 560 nos FHTC given Kannur PH Sn 3 AE
16 Jan 2025 7.8 KM pipe laid 560 nos FHTC given Kannur PH Sn 3 AE
10 Jan 2025 7.8 KM pipe laid 560 nos FHTC given Kannur PH Sn 3 AE
04 Jan 2025 7.8 KM pipe laid 550 nos FHTC given Kannur PH Sn 3 AE
17 Dec 2024 7.8 KM pipe laid 510 nos FHTC given Kannur PH Sn 3 AE
06 Dec 2024 6.5 KM pipe laid 450 nos FHTC given Kannur PH Sn 3 AE