Status Date Overall Project Status Project Officer Contact
04 Jun 2026 valiyannur nayattupara road restoration work is in progress Mattannur WS Sn
21 Apr 2026 Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor. Mattannur WS Sn
13 Apr 2026 Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor. Mattannur WS Sn
04 Apr 2026 Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor. Mattannur WS Sn
26 Mar 2026 Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor. Mattannur WS Sn
18 Mar 2026 Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor. Mattannur WS Sn
09 Mar 2026 Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor. Mattannur WS Sn
27 Feb 2026 Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor. Mattannur WS Sn
17 Feb 2026 Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor. Mattannur WS Sn
04 Feb 2026 Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor. Mattannur WS Sn