Overall Project Status

Status Date Overall Project Status Project Officer Contact
06 Jan 2026 Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor. Mattannur WS Sn
30 Dec 2025 Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor. Mattannur WS Sn
29 Dec 2025 Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor. Mattannur WS Sn
27 Dec 2025 Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor. Mattannur WS Sn
26 Dec 2025 Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor. Mattannur WS Sn
24 Dec 2025 Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor. Mattannur WS Sn
22 Dec 2025 Pipe laying work in pwd road is not completed. hence the restoration work unable to start. all other locations which the pipes were laid area restoration work completed by the contractor. Mattannur WS Sn
22 Dec 2025 Work delayed due to heavy rain,not restarted yet. Mattannur WS Sn
04 Dec 2025 Work delayed due to heavy rain,not restarted yet Mattannur WS Sn
25 Nov 2025 Work delayed due to heavy rain,not restarted yet Mattannur WS Sn