| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 28 Jan 2025 | Earth work started in chola- Nidukulam road | Mattannur WS Sn | |
| 20 Jan 2025 | Earth work started in chola- Nidukulam road | Mattannur WS Sn | |
| 12 Jan 2025 | Earth work started in chola- Nidukulam road | Mattannur WS Sn | |
| 06 Jan 2025 | Earth work started in chola- Nidukulam road | Mattannur WS Sn | |
| 01 Jan 2025 | Earth work started in chola- Nidukulam road | Mattannur WS Sn | |
| 26 Dec 2024 | work not started | Mattannur WS Sn | |
| 18 Dec 2024 | work not started | Mattannur WS Sn | |
| 12 Dec 2024 | work not started | Mattannur WS Sn | |
| 03 Dec 2024 | work not started | Mattannur WS Sn | |
| 25 Nov 2024 | work not started | Mattannur WS Sn |