Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
05 Jan 2021 | 100% work completed | Koothuparamba Project Sn No 1 | |
05 Jan 2021 | Work completed | Koothuparamba Project Sn No 1 | |
05 Jan 2021 | New house connections completed. | Koothuparamba Project Sn No 1 | |
17 Nov 2020 | Pipe laying work completed and charged. Shifting of old house connections and interconnection works are 95% completed .New house connection work progessing. | Koothuparamba Project Sn No 1 | |
16 Nov 2020 | 98% work completed | Koothuparamba Project Sn No 1 | |
25 Aug 2020 | Pipe laying work completed and charged. Shifting of existing house connection and interconnection works are progressing. New house connection work pending. | Koothuparamba Project Sn No 1 |