AMRUT - Kannur Corporation - Rehabilitation of existing distribution network, valves, house service connection and inter connection with existing lines of Pallikkunnu zone

Project AMRUT - Kannur Corporation - Rehabilitation of existing distribution network, valves, house service connection and inter connection with existing lines of Pallikkunnu zone
Project Code KNRAMRUT09172769
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description Rehabilitation of existing distribution network, valves, house service connection and inter connection with existing lines of Pallikkunnu zone.Total distribution line-34735m(600mm-1030,500mm-375m,450mm-660m,400mm-450m,350mm-995m,300mm-610m,250mm-1735m,200mm-2580m and 160mm PVC-26300m).
Status Completed
District Kannur
Executing Office Kannur Project Dn
AS Amount (Rs) 156000000
AS Number
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs) 111509498
Total Bill Paid (Rs) 132709498
Population Benefitted 27820
Capacity in MLD 6.00
Actual Project Completion Date Date is not specified
Coverage 27820(population) 29004(2050) 6125 Habitation

Packages

No. Project Name Location View
1 AMRUT - WSS to Kannur Corporation - Rehabilitation of existing distribution network, valves, house service connection and inter connection with existing lines of Pallikkunnu zone-Package I . Kannur Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 Jan 2021 100% work completed Koothuparamba Project Sn No 1
05 Jan 2021 Work completed Koothuparamba Project Sn No 1
05 Jan 2021 New house connections completed. Koothuparamba Project Sn No 1
17 Nov 2020 Pipe laying work completed and charged. Shifting of old house connections and interconnection works are 95% completed .New house connection work progessing. Koothuparamba Project Sn No 1
16 Nov 2020 98% work completed Koothuparamba Project Sn No 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 16/05/2018
Scheduled date of Completion of the Project 06 Mar 2019
Expected date of Completion 31/12/2020

Processing Dates

AS Date 28 Sep 2017
TS Date 24 Oct 2017
Estimate Approval 24 Oct 2017
Tender Closing 27 Nov 2017
Technichal Pre-Qualification 18 Dec 2017
Price bid opening 19 Dec 2017

Approval Dates

Head Office Approval 03 Mar 2018
Workorder Date 07 Mar 2018
NA 26 Mar 2018