| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 30 Jul 2021 | 665 FHTCs out of 2000 completed | Kallara AE | |
| 27 Jul 2021 | 665 FHTCs out of 2000 completed | Kallara AE | |
| 25 Jul 2021 | 665 FHTCs out of 2000 completed | Kallara AE | |
| 24 Jul 2021 | 650 FHTCs out of 2000 completed and work delayed due to shortage of water meter and most of areas are containment zones after lockdown period. | Aruvikkara HW Dn EE | |
| 19 Jul 2021 | 630 FHTCs out of 2000 completed and work delayed due to shortage of water meter and most of areas are containment zones after lockdown period. | Aruvikkara HW Dn EE | |
| 19 Jul 2021 | 520 FHTCs out of 2000 completed and work delayed due to shortage of water meter and most of areas are containment zones after lockdown period. | Aruvikkara HW Dn EE | |
| 17 Jul 2021 | 520 FHTCs out of 2000 completed and work delayed due to shortage of water meter and most of areas are containment zones after lockdown period. | Aruvikkara HW Dn EE | |
| 12 Jul 2021 | 520 FHTCs out of 2000 completed and work delayed due to shortage of water meter and most of areas are containment zones after lockdown period. | Aruvikkara HW Dn EE | |
| 10 Jul 2021 | 520 FHTCs out of 2000 completed and work delayed due to shortage of water meter and most of areas are containment zones after lockdown period. | Aruvikkara HW Dn EE | |
| 08 Jul 2021 | 420 FHTCs out of 2000 completed and work delayed due to shortage of water meter and most of areas are containment zones after lockdown period. | Aruvikkara HW Dn EE |