| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 10 Aug 2023 | 2300m pipe laid | Koothuparamba Proj AE 2 | |
| 03 Aug 2023 | 2100m pipe laid | Koothuparamba Proj AE 2 | |
| 26 Jul 2023 | Pipe supplying on progress,due to heavy rain work in slow progress | Koothuparamba Proj AE 2 | |
| 19 Jul 2023 | Pipe supplying on progress,due to heavy rain work in slow progress | Koothuparamba Proj AE 2 | |
| 14 Jul 2023 | Pipe supplying on progress,due to heavy rain work in slow progress | Koothuparamba Proj AE 2 | |
| 05 Jul 2023 | Pipe supplying on progress,2000m pipe laid | Koothuparamba Proj AE 2 | |
| 30 Jun 2023 | Pipe supplying on progress,2000m pipe laid | Koothuparamba Proj AE 2 | |
| 23 Jun 2023 | Pipe supplying on progress,700m pipe laid | Koothuparamba Proj AE 2 | |
| 19 Jun 2023 | Pipe supplying and 500m pipe laid | Koothuparamba Proj AE 2 | |