Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
26 Jul 2023 | Pipe supplying on progress,due to heavy rain work in slow progress | Koothuparamba Proj AE 2 | |
19 Jul 2023 | Pipe supplying on progress,due to heavy rain work in slow progress | Koothuparamba Proj AE 2 | |
14 Jul 2023 | Pipe supplying on progress,due to heavy rain work in slow progress | Koothuparamba Proj AE 2 | |
05 Jul 2023 | Pipe supplying on progress,2000m pipe laid | Koothuparamba Proj AE 2 | |
30 Jun 2023 | Pipe supplying on progress,2000m pipe laid | Koothuparamba Proj AE 2 | |
23 Jun 2023 | Pipe supplying on progress,700m pipe laid | Koothuparamba Proj AE 2 | |
19 Jun 2023 | Pipe supplying and 500m pipe laid | Koothuparamba Proj AE 2 | |
12 Jun 2023 | Pipe supply and laying on progress | Koothuparamba Proj AE 2 | |
01 Jun 2023 | pipe supply and laying ongoing | Koothuparamba Proj AE 2 | |
25 May 2023 | DI Pipe supply and Laying started | Koothuparamba Proj AE 2 |