Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 Oct 2022 Pipes laid (1)90 mm PVC -75656 m 2)110mm PVC -7124m 3)140 mm PVC -1236m 4)160 mm PVC-4344.5m ,5)250 mm DI -3299.98m, 6) 400 mm DI - 440.93m 7) 350 mm DI-795.74m ,8)200mm DI -2719.64m,9)300mm DI-1238.67m,10) 450mm DI -364m), Total pipe laid =97219.46m, House connection work in progress. 1900 HTCs provided. Kozhikode Project Dn AE5
26 Sep 2022 Pipes laid (1)90 mm PVC -75656 m 2)110mm PVC -6983m 3)140 mm PVC -1236m 4)160 mm PVC-4344.5m ,5)250 mm DI -3299.98m, 6) 400 mm DI - 440.93m 7) 350 mm DI-795.74m ,8)200mm DI -2719.64m,9)300mm DI-1238.67m,10) 450mm DI -364m), Total pipe laid =97078.46m, House connection and Road Restoration work in progress. 1900 HTCs provided. Kozhikode Project Dn AE5
06 Sep 2022 Pipes laid (1)90 mm PVC -74793 m 2)110mm PVC -6863m 3)140 mm PVC -1236m 4)160 mm PVC-4344.5m ,5)250 mm DI -3299.98m, 6) 400 mm DI - 440.93m 7) 350 mm DI-795.74m ,8)200mm DI -2719.64m,9)300mm DI-1238.67m,10) 450mm DI -364m), Total pipe laid =96095.46m, House connection and Road Restoration work in progress. 1600 HTCs provided. Kozhikode Project Dn AE5
03 Sep 2022 Pipes laid (1)90 mm PVC -74665 m 2)110mm PVC -6863m 3)140 mm PVC -1236m 4)160 mm PVC-4344.5m ,5)250 mm DI -3299.98m, 6) 400 mm DI - 440.93m 7) 350 mm DI-795.74m ,8)200mm DI -2719.64m,9)300mm DI-1238.67m,10) 450mm DI -364m), Total pipe laid =95967.46m, House connection and Road Restoration work in progress. 1112 HTCs provided. Kozhikode Project Dn AE5
25 Aug 2022 Pipes laid (1)90 mm PVC -74469 m 2)110mm PVC -6863m 3)140 mm PVC -1236m 4)160 mm PVC-4344.5m ,5)250 mm DI -3299.98m, 6) 400 mm DI - 440.93m 7) 350 mm DI-795.74m ,8)200mm DI -2719.64m,9)300mm DI-1238.67m,10) 450mm DI -364m), Total pipe laid =95771.46m, House connection and Road Restoration work in progress. 1110 HTCs provided. Kozhikode Project Dn AE5
24 Aug 2022 Pipes laid (1)90 mm PVC -74469 m 2)110mm PVC -6863m 3)140 mm PVC -1236m 4)160 mm PVC-4344.5m ,5)250 mm DI -3299.98m, 6) 400 mm DI - 440.93m 7) 350 mm DI-795.74m ,8)200mm DI -2719.64m,9)300mm DI-1238.67m,10) 450mm DI -354m), Total pipe laid =95761.46m, House connection and Road Restoration work in progress. 1000 HTCs provided. Kozhikode Project Dn AE5
23 Aug 2022 Pipes laid (1)90 mm PVC -74295 m 2)110mm PVC -6863m 3)140 mm PVC -1236m 4)160 mm PVC-4344.5m ,5)250 mm DI -3299.98m, 6) 400 mm DI - 440.93m 7) 350 mm DI-795.74m ,8)200mm DI -2719.64m,9)300mm DI-1238.67m,10) 450mm DI -354m), Total pipe laid =95587.46m, House connection and Road Restoration work in progress. 560 HTCs provided. Kozhikode Project Dn AE5
22 Aug 2022 Pipes laid (1)90 mm PVC -74295 m 2)110mm PVC -6863m 3)140 mm PVC -1236m 4)160 mm PVC-4344.5m ,5)250 mm DI -3299.98m, 6) 400 mm DI - 440.93m 7) 350 mm DI-795.74m ,8)200mm DI -2719.64m,9)300mm DI-1238.67m,10) 450mm DI -354m), Total pipe laid =95587.46m, House connection and Road Restoration work in progress. Kozhikode Project Dn AE5
16 Aug 2022 Pipes laid (1)90 mm PVC -74295 m 2)110mm PVC -6863m 3)140 mm PVC -1236m 4)160 mm PVC-4344.5m ,5)250 mm DI -3299.98m, 6) 400 mm DI - 440.93m 7) 350 mm DI-795.74m ,8)200mm DI -2719.64m,9)300mm DI-1238.67m,10) 450mm DI -354m), Total pipe laid =95587.46m, House connection and Road Restoration work in progress. Kozhikode Project Dn AE5
04 Aug 2022 Pipes laid (1)90 mm PVC -74295 m 2)110mm PVC -6863m 3)140 mm PVC -1236m 4)160 mm PVC-4344.5m ,5)250 mm DI -3299.98m, 6) 400 mm DI - 440.93m 7) 350 mm DI-795.74m ,8)200mm DI -2719.64m,9)300mm DI-1238.67m,10) 450mm DI -354m), Total pipe laid =95587.46m, House connection work in progress. Kozhikode Project Dn AE5